Wisconsin Code § 289.23

Feasibility report required; distribution; public notice
Open in Lexace · Ask the AI about this section
(1) FEASIBILITY REPORT REQUIRED. Prior to constructing a solid waste disposal facility or a hazardous waste facility the person who seeks to construct the facility shall submit
to the department a feasibility report.
(2) LOCAL APPROVAL APPLICATION PREREQUISITE. No person subject to s. 289.33 may submit a feasibility report until the
latest of the following periods:
(a) At least 120 days after the person submits applications for
all applicable local approvals specified as required by the municipality under s. 289.22 (1m).
(b) At least 120 days after the receipt by the applicant of a
statement by the municipality that there are no applicable local
approvals.
(c) At least 120 days after the deadline for the municipal response under s. 289.22 (1m) if the municipality does not respond
within that time limit.
(3) COMPLIANCE REQUIRED. No person may construct a solid
waste disposal facility or a hazardous waste facility unless the
person complies with the requirements of ss. 289.23 to 289.29.
(4) DISTRIBUTION OF FEASIBILITY REPORT. At the same time
an applicant submits a feasibility report to the department, the
applicant shall submit a copy of that feasibility report to each participating municipality under s. 289.33 (6) (b).
(5) NOTIFICATION OF PROPOSED FACILITY. Immediately upon
receipt of a feasibility report the department shall send a notice to
the persons specified under s. 289.32 containing a brief description of the proposed facility and a statement that the applicant is
required to send a copy of the feasibility report after it is determined to be complete by the department.

‹ Prev All Wisconsin sections Next ›