West Virginia Code § 24-2-1e

Rate recovery for construction of electric transmission facilities
Open in Lexace · Ask the AI about this section
In order to encourage the construction of transmission facilities necessary to transmit
electric power from generating facilities located in this state to areas where such power can
be economically marketed, the commission may allow an electric utility accelerated rate
recovery for transmission facilities constructed or upgraded for the purpose of increasing
the capacity to transmit electric power to areas outside the utility's service eterritory where
such power can be economically marketed. In allowing accelerated rate recovery, the
commission shall include the impact of the investment in transmission rfacilities on any
investment equalization agreement in which the utilities participate.