West Virginia Code § 24-2-1d

Future electric generating capacity requirements
Open in Lexace · Ask the AI about this section
(a) In order to maximize the use of electricity generated within the state by using coal or
natural gas produced within the state, the Public Service Commission shall by order, no later
than December 31, 1989, establish the schedule and amount of future electric generating
capacity additions required by each West Virginia electric utility, for the next ten years,
taking into account: (i) Projected load growth; (ii) existing generating capaceity; (iii) existing
contractual commitments to sell or purchase capacity; (iv) planned retirement and life
extensions of existing capacity; (v) planned construction of capacity; (vri) availability of
capacity from generating units of affiliated companies; (vii) capacity factors for existing
generation; and (viii) such other reasonable factors as the commission may deem relevant
and appropriate to consider. For purposes of this section, "capacity factor" shall mean the
ratio of the actual energy produced by a power plant over a tspecific period to the maximum
possible energy it could have produced if running at full capacity during that same period.
(b) If the commission determines after considering all such named and other relevant and
appropriate factors that a utility will be required to purchase electric generating capacity
beyond those agreements approved by the Fesderal Energy Regulatory Commission or the
West Virginia Public Service Commission in order to serve its West Virginia customers, the
amount of such required additional purchased capacity so identified by the commission will
for purposes of this section be referrged to as the utility's "projected deficient capacity":
Provided, That this subsection shall not include power generating facilities whose total
production of electricity is solde outside the State of West Virginia.
(c) In the interests of: KLeeping utility rates of residential customers as low as possible;
keeping utility rates for commercial and industrial customers competitive with those of other
states; attracting new industry for which electric power costs are a major factor in location
determinations; and of not placing any greater cost burden on government than is absolutely
necessary for its electric power needs, each utility shall acquire, if reasonable, its projected
deficient capacity from electric generation situated in West Virginia which burns coal or gas
proWduced in West Virginia and which will provide the most reliable supply of capacity and
energy at the least cost to those customers of the utility who will be served by such electric
generation: Provided, That all power purchase contracts executed prior to the effective date
of this section which satisfy the following requirements, regardless of location, shall be
considered, for the purposes of this subsection, as electric generation situated in West
Virginia: (1) Said contracts were negotiated in accordance with procedures and priced
according to methodologies of other contracts which the commission has ordered approved;
(2) said contracts either guarantee or are substantially amended to guarantee for the life of
the contract the use of an amount of West Virginia fuel which equals or exceeds the amount
which would be required, on a percentage of output basis, to produce the amount of electric
power to be consumed in West Virginia; and (3) said contracts meet the requirements for a
qualifying facility established by the Federal Energy Regulatory Commission pursuant to the
Public Utility Regulatory Policies Act of 1978.
(d) The commission shall evaluate each capacity auction conducted by PJM Interconnection,
LLC, or its successor and, to the maximum extent permitted by law, encourage the
coordination of the voluntary participation of every electric generating unit in the state in
each capacity auction for the benefit of ratepayers in the state.
(e) In order to ensure the state's existing generating units can continue to meet future
generation needs, the commission shall conduct a review of each generating unit's current
consumer economic dispatch. Factors to be considered by the commission ine reviewing
consumer economic dispatch shall include, but not be limited to: (1) current capacity factors;
(2) management of fuel supplies and contracts; (3) overall plant operatrion and maintenance;
(4) placement of bids in the PJM Interconnection, LLC, or its successor's day-ahead and real-
time energy markets; (5) utilization of the PJM Interconnection, LLC, or its successor's
Reliability Pricing Model (RPM) or Fixed Resource Requirement (FRR); and (6) the
utilization of automatic adjustment clauses, price indexes, ort fuel adjustment clauses by the
utilities. For purposes of this section, "consumer economic dispatch" shall mean the process
of operating generation facilities to produce electricity at the lowest cost while reliably
meeting consumer demand, considering the operational limits of generation and
transmission facilities.
(f) Electric utilities shall be prepared to maximize the production of electricity from their
generating units when such self-generation will result in reduced energy costs for West
Virginia ratepayers. The commissiong shall require the utilities to maintain their thermal
baseload generating units in a manner to allow them to be able to self-generate and achieve
at least a sixty-nine percent caepacity factor. Nothing herein shall require a utility to operate
a generating unit at a sixty-nine percent capacity if doing so will cause an increase in the
charge or charges for elLectric energy over and above the established and published tariff,
rate, joint rate, charge, toll or schedule. The commission shall propose rules for legislative
approval in accordan ce with the provisions of §29A-3-1 et seq. of this code to carry out its
duties and obligations as set forth herein.

‹ Prev All West Virginia sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.