West Virginia Code § 22-3-12

Site-specific bonding; legislative rule; contents of legislative rule;
Open in Lexace · Ask the AI about this section
legislative intent.
(a) Notwithstanding the provisions of section eleven of this article, the secretary may
establish and implement a site-specific bonding system in accordance with the provisions of
this section.
(b) A legislative rule proposed or promulgated pursuant to this section must provide, at a
minimum, for the following:
(1) The penal amount of a bond shall be not less than $1,000 noru more than $5,000 per acre
or fraction thereof.
(2) Every bond, subject to the limitations of subdivision (1) of this subsection, shall reflect
the relative potential cost of reclamation associated wiath the activities proposed to be
permitted, which would not otherwise be reflected by bonds calculated by merely applying a
specific dollar amount per acre for the permit. l
(3) Every bond, subject to the provisions of subdivision (1) of this subsection, shall also
reflect an analysis under the legislative ruile of various factors, as applicable, which affect
the cost of reclamation, including, but not limited to: (A) The general category of mining,
whether surface or underground; (B) mining techniques and methods proposed to be
utilized; (C) support facilities, fixtures, improvements and equipment; (D) topography and
geology; and (E) the potential for degrading or improving water quality.
(c) A legislative rule proposed or promulgated pursuant to the provisions of this section may,
in addition to the requirements of subsection (b) of this section, provide for a consideration
of other factors deter mined to be relevant by the secretary. For example, the rule may
provide for thVe following:
(1) A consideration as to whether the bond relates to a new permit application, a renewal of
an existing permit, an application for an incidental boundary revision or the reactivation of
an inactive permit;
(2) A consideration of factors which may result in environmental enhancement, as in a case
where remining may improve water quality or reduce or eliminate existing highwalls, or a
permitted operation may create or improve wetlands; or
(3) An analysis of various factors related to the specific permit applicant, including, but not
limited to: (A) The prior mining experience of the applicant with the activities sought to be
permitted; and (B) the history of the applicant as it relates to prior compliance with statutory
and regulatory requirements designed to protect, maintain or enhance the environment in
this or any other state.
(d) It is the intent of the Legislature that a legislative rule proposed or promulgated
pursuant to the provisions of this section shall be constructed so that when the findings of
fact by the Division of Environmental Protection with respect to the proposed mining activity
and the particular permit applicant coincide with the particular factors or criteria to be
considered and analyzed under the rule, the rule will direct a conclusion as to the amount of
the bond to be required, subject to rebuttal and refutation of the findings by the applicant.
To the extent practicable, the rule shall limit subjectivity and discretion by the secretary and
the division in fixing the amount of the bond.