Texas Code § 37.057

DEADLINE FOR APPLICATION FOR NEW TRANSMISSION FACILITY
Open in Lexace · Ask the AI about this section
Sec. 37.057. DEADLINE FOR APPLICATION FOR NEW TRANSMISSION FACILITY. The commission must approve or deny an application for a certificate for a new transmission facility not later than the 180th day after the date the application is filed. If the commission does not approve or deny the application on or before that date, a party may seek a writ of mandamus in a district court of Travis County to compel the commission to decide on the application.

‹ Prev All Texas sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.