Nevada Code § 338.595

Amounts withheld as retainage; payment of interest
Open in Lexace · Ask the AI about this section
1. If a subcontractor and another
subcontractor or supplier enter into a subcontract for a public work, the
subcontractor may withhold as retainage not more than 5 percent from the amount
of any progress payment due under a subcontract which is made before 50 percent
of the work has been completed under the subcontract.
2. After 50 percent of the work required
by the subcontractor or supplier has been performed, the subcontractor shall
pay any additional progress payments due under the subcontract without
withholding any additional retainage if, in the opinion of the subcontractor,
satisfactory progress is being made in the work under the subcontract. The
payment must be equal to that paid by the contractor to the subcontractor for
the work performed or supplies provided by his or her subcontractor or
supplier. If the subcontractor continues to withhold retainage from remaining
progress payments:
(a) If the subcontractor does not withhold any
amount pursuant to NRS 338.600 :
(1) The subcontractor may not withhold more
than 2.5 percent of the amount of any progress payment; and
(2) Before withholding any amount pursuant
to subparagraph (1), the subcontractor must pay to the subcontractor or
supplier 50 percent of the amount of any retainage that was withheld from progress
payments pursuant to subsection 1; or
(b) If the subcontractor withholds any amount
pursuant to NRS 338.600 :
(1) The subcontractor may not withhold
more than 5 percent of the amount of any progress payment; and
(2) The subcontractor may continue to
retain the amount of any retainage that was withheld from progress payments
pursuant to subsection 1.
3. If the subcontractor receives a payment
of interest earned on the retainage or an amount withheld from a progress
payment, the subcontractor shall, within 10 days after receiving the money, pay
to each of his or her subcontractors or suppliers that portion of the interest
received from the contractor which is attributable to the retainage or amount
withheld from a progress payment by the subcontractor to his or her
subcontractor or supplier.
4. If, pursuant to subsection 4 of NRS 338.555 , the contractor pays to the subcontractor
the portion of any retainage withheld by the contractor pursuant to NRS 338.555 for the portion of the work
which has been performed by the subcontractor, the subcontractor must pay to
the subcontractors subcontractors and suppliers the portion of any retainage
withheld by the subcontractor pursuant to this section for the portion of the
work.

‹ Prev All Nevada sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.