Nevada Code § 338.590

Time for making payments; amounts paid
Open in Lexace · Ask the AI about this section
Except
as otherwise provided in NRS 338.595 , 338.600 and 338.605 :
1. Each subcontractor shall disburse money
paid to him or her pursuant to this chapter, including any interest which the
subcontractor receives, to his or her subcontractors and suppliers within 10
days after the subcontractor receives the money, in direct proportion to the
subcontractors and suppliers basis in the progress bill or retainage bill and
any accrued interest thereon.
2. A subcontractor shall make payments to
his or her subcontractor or supplier in an amount equal to that subcontractors
or suppliers basis in the payments paid by the contractor to him or her for
the supplies, materials and equipment identified in the contract between the
contractor and the public body, or in the subcontract between the subcontractor
or supplier and the contractor, within 10 days after the subcontractor has
received a progress payment or retainage payment from the contractor for those
supplies, materials and equipment.