Within 5 working days after a public body receives a written request from a subcontractor or supplier of the contractor with respect to a contract which has not been fully performed, the public body shall notify the subcontractor or supplier in writing of the following: 1. The date the public body made a specified progress payment or retainage payment to a contractor; 2. Whether the public body has paid the entire amount of a specified progress payment or retainage payment to the contractor; and 3. The amount withheld by the public body from a specified progress payment or retainage payment to the contractor, if any.