Nevada Code § 338.535

Public body to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers
Open in Lexace · Ask the AI about this section
Within 5 working days after a public body
receives a written request from a subcontractor or supplier of the contractor
with respect to a contract which has not been fully performed, the public body
shall notify the subcontractor or supplier in writing of the following:
1. The date the public body made a
specified progress payment or retainage payment to a contractor;
2. Whether the public body has paid the
entire amount of a specified progress payment or retainage payment to the
contractor; and
3. The amount withheld by the public body
from a specified progress payment or retainage payment to the contractor, if
any.