Nevada Code § 338.530

Payment of interest on amounts withheld improperly
Open in Lexace · Ask the AI about this section
1. If a public body receives:
(a) A progress bill or retainage bill, fails to
give a contractor a written notice of any withholding in the manner set forth
in subsection 2 of NRS 338.525 , and does
not pay the contractor within 30 days after receiving the progress bill or
retainage bill; or
(b) A contractors written notice of the
correction of a condition set forth pursuant to subsection 2 of NRS 338.525 as the reason for the
withholding, signed by an authorized agent of the contractor, and fails to:
(1) Pay the amount of the progress payment
or retainage payment that was withheld from the contractor within 30 days after
the public body receives the next progress bill or retainage bill; or
(2) Object to the scope and manner of the
correction, within 30 days after the public body receives the notice of
correction, in a written statement that sets forth the reason for the objection
and is signed by an authorized agent of the public body,
the public
body shall pay to the contractor, in addition to the entire amount of the
progress bill or retainage bill or any unpaid portion thereof, interest from
the 30th day on the amount delayed, at a rate equal to the amount provided for
in subsection 6 of NRS 338.515 , until
payment is made to the contractor.
2. If the public body objects pursuant to
subparagraph (2) of paragraph (b) of subsection 1, it shall pay to the
contractor an amount equal to the value of the corrections to which the public
body does not object.

‹ Prev All Nevada sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.