Maryland Code § PU-7-306.1

Section PU-7-306.1
Open in Lexace · Ask the AI about this section
(a) A person who is negotiating a contract with an eligible customer-
generator to install a solar electric generating facility on the customer-generator's
property that the customer-generator owns and operates, leases and operates, or
contracts with a third party that owns and operates and that requires interconnection
with an electric company's distribution facilities:
(1) shall submit to the customer-generator's electric company a
completed application for interconnection of the solar electric generating facility with
the electric company's distribution facilities;
(2) before receiving the electric company's approval of the application
submitted under paragraph (1) of this subsection:
(i) may accept payment from the customer-generator in
connection with the contract; but
(ii) may not begin installation of the solar electric generating
facility on the customer-generator's property;

(3) shall notify the customer-generator of the electric company's
approval or disapproval of the application submitted under paragraph (1) of this
subsection; and
(4) if the electric company disapproves the application submitted
under paragraph (1) of this subsection, shall fully refund any payment from the
customer-generator under paragraph (2)(i) of this subsection.
(b) On request of a person under subsection (a)(1) of this section, an electric
company shall process an application submitted under subsection (a)(1) of this section
and notify the person whether the application is approved or disapproved in
accordance with a process and time frame specified in regulations adopted by the
Commission.
(c) (1) In this subsection, "installation process" includes:
(i) an approved application submitted under subsection (a)(1)
of this section;
(ii) completion of the installation of the customer-generator's
solar electric generating facility and any required electric distribution system
upgrades; and
(iii) completion of all necessary paperwork and documentation,
including a signed interconnection agreement, certificate of completion, and an
inspection certificate.
(2) (i) Subject to subparagraph (ii) of this paragraph, an electric
company shall issue acceptance and final approval to operate a customer-generator's
solar electric generating facility on the electric company's distribution facilities
within 20 business days after the completion of the installation process and receipt
of the paperwork and documentation set forth in paragraph (1)(iii) of this subsection.
(ii) An electric company shall complete the interconnection
requirements under subparagraph (i) of this paragraph for at least 90% of installation
processes completed during the year in the electric company's service territory.
(3) The Commission may temporarily waive the requirements under
paragraph (2) of this subsection in an electric company's service territory on a
showing of good cause.