Maryland Code § PU-7-1212

Section PU-7-1212
Open in Lexace · Ask the AI about this section
(a) (1) After the effective date of Commission regulations implementing
this part, a person may submit an application to the Commission for approval of a
proposed nuclear energy generation project, including an application to upgrade the
generation capabilities of an existing nuclear energy generating station.
(2) For an application submitted in accordance with paragraph (1) of
this subsection, the long-term pricing schedule shall be based only on any new
generation proposed in the application, including new generation at an existing
nuclear energy generating station.
(b) (1) On receipt of an application for approval of a proposed nuclear
energy generation project, the Commission shall:
(i) open an application period during which other interested
persons may submit applications for approval of a proposed nuclear energy
generation project; and

(ii) provide notice that the Commission is accepting
applications for approval of proposed nuclear energy generation projects.
(2) The Commission shall set the closing date for the application
period to be not sooner than 90 days after the notice provided under paragraph (1) of
this subsection.
(c) The Commission shall provide at least two additional application
periods before January 1, 2031.
(d) The Commission may provide additional application periods that meet
the requirements of this section.