(a) Before a utility authorizes electrical current to be turned on for a
premise or structure, the utility must receive a cut-in certificate from a certified
nongovernmental electrical inspector or governmental unit that is qualified to issue
electrical inspection certificates.
(b) Within 15 days after completion, each electrical installation shall be
certified by a certified nongovernmental electrical inspector or a governmental unit
that is qualified to issue electrical inspection certificates.