Maine Code § 32-15105

Installation of new boilers and pressure vessels
Open in Lexace · Ask the AI about this section
A new boiler or pressure vessel that does not conform to the rules adopted by the director governing
new installations may not be installed in this State. [PL 2013, c. 70, Pt. C, §14 (AMD).]
Unless otherwise exempt, all new boilers and pressure vessels to be installed must be inspected
during construction by an inspector authorized to inspect boilers in this State, or, if constructed outside
the State, by an inspector holding a license from this State or an inspector who holds a certificate of
inspection issued by the National Board of Boiler and Pressure Vessel Inspectors, or its successor or
other organization approved by the director. [PL 2013, c. 70, Pt. C, §14 (AMD).]