1. Definitions. As used in this section, unless the context otherwise indicates, the following terms
have the following meanings.
A. "Department" means the Department of Transportation. [PL 1999, c. 468, §2 (NEW).]
A-1. "High-speed rural arterial highway" means an arterial highway as defined in section 704 that
is not located in the urban compact area of an urban compact municipality as described in section
754 and where the posted speed limit at the time of the application for a traffic movement permit
is 40 miles per hour or greater. [PL 2003, c. 363, §1 (NEW).]
B. "Passenger car equivalents at peak hour" means the number of passenger cars or, in the case of
nonpassenger vehicles, the number of passenger cars that would be displaced by nonpassenger
vehicles at that hour of the day during which the traffic volume generated by the development is
higher than the volume during any other hour of the day. For purposes of this paragraph, one
tractor-trailer combination is the equivalent of 2 passenger cars. [PL 1999, c. 468, §2 (NEW).]
C. "Project" includes any construction, alteration or conversion of a building, or any development
of state or regional significance that may substantially affect the environment as defined in Title
38, section 482, subsection 2. [PL 1999, c. 468, §2 (NEW).]
D. "Traffic demand management techniques" means measures taken to reduce or spread peak hour
traffic over a longer period of time. Such measures include, but are not limited to, on-site facilities
or on-site design considerations to support local, regional or state bicycle, pedestrian, passenger
rail, transit and ride-sharing efforts or plans. The department may not require operational support
of passenger transportation systems or require parking management strategies of the permit
applicant. [PL 2003, c. 363, §2 (NEW).]
[PL 2003, c. 363, §§1, 2 (AMD).]
2. Permit. A traffic movement permit must be obtained from the department for any project that
generates 100 or more passenger car equivalents at peak hour. A person receiving a permit under this
section is not required to obtain a permit pursuant to section 704.
A. For any project that generates 100 or more passenger car equivalents at peak hour, the person
responsible for the project is required to make adequate provision for traffic movement of all types
into and out of the project area. Before issuing a permit, the department shall determine that any
traffic increase attributable to the proposed project will not result in unreasonable congestion or
unsafe conditions on a road in the vicinity of the proposed project. [PL 1999, c. 468, §2 (NEW).]
B. The department, together with the appropriate representative of the municipality or
municipalities where the project is located, shall discuss with the applicant at a meeting, referred
to in this paragraph as a "scoping meeting," the scope of impact evaluation required for the
proposed project and the type of proceedings warranted. The applicant shall provide notice to
abutting municipalities. If the department determines as a result of these communications that the
applicant has demonstrated that the proposed project satisfies standards adopted for projects that
generate 100 to 200 passenger car equivalents at peak hour and the department determines that

there are no other significant traffic-related issues presented, the department may issue a permit to
the applicant without further proceedings. The department shall adopt rules establishing the
submission requirement for a scoping meeting. Those rules must, at a minimum, establish 2
submission standards: one for an expedited review without further proceedings and one for a
preliminary review with further proceedings anticipated. The rules must also establish the level of
professional certification required by any submission and may not impose undue professional
liability on the applicant. [PL 1999, c. 468, §2 (NEW).]
C. [PL 2003, c. 363, §3 (RP).]
D. If a project is located in an area designated as a growth area in a local growth management plan
that has been found by the State to be consistent with the growth management program in Title
30-A, chapter 187 and the project does not have an entrance or exit located on a high-speed rural
arterial highway and the applicant for a traffic movement permit implements traffic demand
management techniques recommended by the department, then the required improvements are
limited:
(1) To those necessary to mitigate the impact of the project provided all safety standards are
met, even if part or all of the traffic impact occurs outside the boundaries of the growth area;
and
(2) To the entrances and exits of the project, if the project reuses previously developed land
area and buildings with no more than a 10% increase in building footprint regardless of the
extent of vertical development. [PL 2003, c. 363, §4 (RPR).]
E. Adequate provision for traffic movement may be provided through payment of funds pursuant
to section 57-A. [PL 1999, c. 468, §2 (NEW).]
F. Prior to issuing a traffic movement permit, the department must find that the applicant has right,
title or interest to the property necessary to execute the traffic-related conditions of the permit, and
that no inconsistent control of access provision exists with respect to access to the property. The
department shall also advise the applicant that following issuance of the permit yet prior to
construction of any improvements affecting the right-of-way of the department, the applicant must
demonstrate through a developer agreement the financial, legal and technical ability to develop
such improvements. [PL 1999, c. 468, §2 (NEW).]
[PL 2003, c. 363, §§3, 4 (AMD).]
3. Exemptions. A permit is not required for any project reviewed under Title 38, section 1310-N,
1319-R or 1319-X. A permit is not required for any project exempt from review under Title 38, chapter
3, subchapter I, article 6 pursuant to Title 38, section 488, subsection 7 or subsection 18.
[PL 1999, c. 468, §2 (NEW).]
4. Registered municipalities. The department may register municipalities for issuing traffic
movement permits under this section for projects generating 100 or 200 passenger car equivalents at
peak hours upon finding that:
A. The municipality has in effect an ordinance or regulation for reviewing traffic movement
permits that is consistent with the policy and purpose of this section; and [PL 1999, c. 468, §2
(NEW).]
B. The ordinance or regulation is administrable and enforceable and will be properly administered
and enforced. [PL 1999, c. 468, §2 (NEW).]
Whenever any of the conditions set forth in this subsection are no longer being met, the department
shall resume promptly the administration of reviewing traffic movement permits upon written notice to
the municipality.

Upon a determination by the department that there will be no adverse traffic impact in a municipality
other than the municipality in which the project is located, the department may register any municipality
for issuing traffic movement permits under this section for any project generating more than 200
passenger car equivalents at peak hour.
The department may provide technical assistance to municipalities upon request for projects reviewed
under this section.
The department may review projects for registered municipalities if the local reviewing authority for
the municipality in which the project is located petitions the department in writing. Any neighboring
municipality affected by the project may petition the department in writing to review the project no
later than 30 days after it has been approved by the local reviewing authority.
[PL 1999, c. 468, §2 (NEW).]
5. Reconsideration. Requests for reconsideration by the commissioner under this subsection must
be made in accordance with this subsection. Nothing in this subsection may be construed to limit a
person's lawful right to appeal a final agency action.
If the department issues an order without a hearing, a person may request reconsideration by the
department within 30 days after notice of the department's decision. This request must set forth, in
detail, the findings and conclusions of the department to which that person objects, the basis of the
objections and the nature of the relief requested. Upon receipt of the request, the department may
schedule and hold a hearing limited to the matters set forth in the request.
[PL 1999, c. 468, §2 (NEW).]
6. Fees. The department shall assess fees for the issuance and processing of a permit under this
section. Fees may not exceed $500 for issuance of a permit following a scoping meeting as described
in section 704-A, subsection 2, paragraph B, with no further review. Fees may not exceed $2,000 for
issuance of a permit requiring review beyond a scoping meeting.
[PL 1999, c. 468, §2 (NEW).]
7. Consolidation. If an applicant is required to obtain both a permit from the department pursuant
to this section and a permit under the site location of development laws from the Department of
Environmental Protection pursuant to Title 38, chapter 3, subchapter I, article 6, the applicant may
either apply individually to each agency for the appropriate permit or request that the department and
the Department of Environmental Protection provide a consolidated application process.
A. On the request of an applicant prior to the submission of applications for permits pursuant to
this section and Title 38, chapter 3, subchapter I, article 6, the department and the Department of
Environmental Protection shall provide a consolidated application process. As long as an
application is not withdrawn, the process must result in a consolidated order issued by both the
department and the Department of Environmental Protection, either approving or denying the
applicable permits. Any necessary findings or conditions relevant to the individual permits must
be separately identified in the order. All applicable fees and the longer of the applicable processing
times apply. The processing period may be extended pursuant to Title 38, section 344-B,
subsection 3 or if a hearing is required pursuant to subsection 5. [PL 1999, c. 468, §2 (NEW).]
B. If an aggrieved party seeks an administrative appeal of a consolidated order, and there are issues
relevant to both permits, the department and the Department of Environmental Protection shall
provide a consolidated administrative appeal process. If there are issues relevant to only one
permit, the relevant portion of the order may be appealed to the appropriate agency. [PL 1999, c.
468, §2 (NEW).]
C. The department and the Department of Environmental Protection shall enter into a
memorandum of agreement establishing procedures for coordination of the consolidated

application process and the consolidated administrative appeal process by June 30, 1999. [PL
1999, c. 468, §2 (NEW).]
This subsection does not apply to a project reviewed by a municipality under subsection 4 or Title 38,
section 489-A.
[PL 1999, c. 468, §2 (NEW).]
8. Modification of existing permits. A permit issued under Title 38, chapter 3, subchapter 1,
article 6 prior to the effective date of this section may be modified by the department to address issues
relating to traffic movement and adequate provision of roads. At the department's request, a person
holding such a permit shall send a copy of the permit application to the department and to the
Department of Environmental Protection. The department shall notify the Department of
Environmental Protection of any substantive changes in the permit and shall provide that department
with a copy of the final revised permit.
[PL 1999, c. 468, §2 (NEW).]
9. Rules. Rules adopted under this section are major substantive rules pursuant to Title 5, chapter
375, subchapter II-A.
[PL 1999, c. 468, §2 (NEW).]
10. Violation. A violation of this section or the rules adopted pursuant to this section is punishable
by a fine of not more than $100 per day per violation. The fine begins to accrue 30 days after the
Department of Transportation sends notice of the violation to the landowner. The department shall
establish procedures for administrative enforcement of this section, establishing fines and
reconsideration and appeals of enforcement actions.
[PL 2003, c. 363, §5 (NEW).]

‹ Prev All Maine sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.