Maine Code § 10-1488

Change orders
Open in Lexace · Ask the AI about this section
Each change order to a home construction contract must be in writing and becomes a part of and is
in conformance with the existing contract. All work shall be performed under the same terms and
conditions as specified in the original contract unless otherwise stipulated. The change order must
detail all changes to the original contract that result in a revision of the contract price. The previous
contract price must be stated and the revised price shall also be stated. Both parties must sign the
change order. [PL 1987, c. 574 (NEW).]