(1) (a) In the event an order of a division
engineer or the state engineer issued pursuant to section 37-92-502 is not complied with, the
state engineer and the particular division engineer in the name of the people of the state of
Colorado, through the attorney general, shall apply to the water judge of the particular division
for an injunction enjoining the person to whom such order was directed from continuing to
violate same. The term "injunction" includes mandatory relief.
(b) In such proceeding, if the court upholds the order of the state engineer, the person
against whom such order was issued shall pay the costs of the proceeding, including the
allowance of reasonable attorney fees.
(c) Any proceeding brought by the state engineer or a division engineer to enforce an
order to curtail the diversion of surface water or groundwater to comply with an interstate
compact shall be accelerated on the court's calendar pursuant to section 37-92-203 (2), shall take
priority over other water matters, and shall be determined immediately upon the conclusion of
such proceeding.
(2) In the case of an order with respect to the diversion of water or the release of water
from reservoirs, the water judge in ruling upon such injunction shall consider, depending on the
basis for the order, whether or not the water is being applied to a beneficial use; whether or not
the diversion is causing or will cause injury to persons owning, or entitled to use water under,
water rights having senior decreed priorities; and whether or not the release of improperly stored
water would benefit other water users.
(3) Any person who has an interest in the subject matter of such proceedings may
intervene, if such intervention is timely and will not cause undue delay.
(4) In the case of a violation of an injunction issued under the provisions of this section,
the water judge shall try and punish the offender for contempt of court.
(5) Such proceedings shall be in addition to, and not in lieu of, any other penalties and
remedies, public or private, provided by law.
(6) (a) (I) Any person who diverts groundwater contrary to a valid order of the state
engineer or a division engineer issued pursuant to section 37-92-502, in violation of a plan
approved pursuant to rules adopted by the state engineer, or otherwise in violation of rules
adopted by the state engineer to regulate or measure diversions of groundwater shall forfeit and
pay a sum not to exceed five hundred dollars for each day such violation continues.
(II) Any person who diverts surface water contrary to a valid order of the state engineer
or a division engineer issued pursuant to section 37-92-502 shall forfeit and pay a sum not to
exceed five hundred dollars for each day such violation continues.
(b) Any person who, when required to do so by rules and regulations adopted by the
state engineer, fails to submit data as to amounts of water pumped from a well, makes a false or
fictitious report of the amounts of water pumped from a well, falsifies any data as to amounts
pumped from a well, makes a false or fictitious report of a power coefficient for a well, or
falsifies any power coefficient test shall forfeit and pay a sum not to exceed five hundred dollars
for each violation.
(c) It is unlawful for any person not authorized by the well owner or the state engineer to
willfully interfere with any power meter, totalizing flow meter, or other device used to measure
groundwater diversions. Any person who willfully injures or destroys a power meter, totalizing
flow meter, or other device used to measure groundwater diversions or who tampers with or
falsifies any record made or being made by any such power meter, totalizing flow meter, or other
device shall forfeit and pay a sum not to exceed five hundred dollars for each violation.
(d) Any fine collected for violations of the provisions of this subsection (6) shall be
transmitted to the state treasurer, who shall credit the same to the general fund.
(e) The state engineer and the particular division engineer in the name of the people of
the state of Colorado, through the attorney general, shall apply to the water judge of the
particular division to recover the civil penalties specified in paragraphs (a), (b), and (c) of this
subsection (6) or for a temporary restraining order, preliminary injunction, or permanent
injunction, as appropriate, enjoining further violations of this subsection (6). If the state engineer
and the division engineer prevail, the court shall also award the costs of the proceeding including
the allowance of reasonable attorney fees.
(7) Any person required by a valid order of the state engineer or division engineer, or by
existing rules of the state engineer, to replace depletions caused by diversions of groundwater or
surface water and whose failure to replace such depletions results in the violation of an interstate
compact shall be liable for all direct, actual, and necessary expenses incurred by the state of
Colorado in performing any action, including the purchase of water or payment of damages,
necessary for the state of Colorado to remedy the violation of such compact. The state engineer
and the particular division engineer in the name of the people of the state of Colorado, through
the attorney general, shall apply to the water judge of the particular division to recover such
expenses. If the state engineer and the division engineer prevail, the court shall also award the
costs of the proceeding including the allowance of reasonable attorney fees.
(8) Repealed.
(9) In the case of an action initiated by the state engineer or another person alleging
expanded or unlawful use of a water right decreed for irrigation, the lawful maximum amount of
irrigated acreage for a decree entered before January 1, 1937, that establishes an irrigation water
right and does not expressly limit the number of acres that the appropriator may irrigate under
the water right equals the maximum amount of acreage irrigated in compliance with the express
provisions of the decree during the first fifty years after the entry of the original decree, unless a
court of competent jurisdiction has entered a final judgment to the contrary. Irrigation of acreage
not exceeding the lawful maximum amount and located within a reasonable proximity to the
ditch, including extensions and lateral delivery infrastructure, as constructed within the first
fifty-year period after entry of the original decree is deemed lawful for continued irrigation
under the water right.