Wisconsin Code § 88.72

Removal of dams or other obstructions in drainage outlets
Open in Lexace · Ask the AI about this section
(1) The owners of more than one-tenth of
the lands within any district may file with the drainage board a
petition setting forth:
(a) That the drains constructed within such district do not afford an adequate outlet for drainage;
(b) That it is necessary in order to give an adequate outlet to
remove certain dams or other obstructions from waters or streams
or to deepen, straighten or widen the same either within or beyond the boundaries of such district; and
(c) That the public health and the public welfare will be promoted by such work and that the navigability of such waters or
streams and other public rights therein will not be materially
impaired.
(2) Upon receiving a petition under sub. (1), the drainage
board shall fix a time and place of a hearing on the petition and
shall cause notice of the hearing to be given under s. 88.05 (2) (b)
to the persons specified in s. 88.05 (4) (a) , to the owner of any
dam sought to be removed and to all riparian owners affected by
the removal.
(3) At the hearing on the petition, any interested person may
appear and contest its sufficiency and the necessity for the work.
If the drainage board finds that the petition has the proper number
of signers and that to afford an adequate outlet it is necessary to
remove dams or other obstructions from waters and streams
which may be navigable, or to straighten, clean out, deepen or
widen any waters or streams either within or beyond the limits of
the district, the board shall obtain any permit that is required under this chapter or ch. 30 or 31.
(4) Within 30 days after the department of natural resources
has issued all of the permits as required under this chapter and
chs. 30 and 31, the board shall proceed to estimate the cost of the
work, including the expenses of the proceeding together with the
damages that will result from the work, and shall, within a reasonable time, award damages to all lands damaged by the work
and assess the cost of the work against the lands in the district in
proportion to the assessment of benefits then in force.
(5) The drainage board may grant the petition and order the
additional work done only if the drainage board is satisfied that:
(a) The intended result can be effectively achieved by additional work at a reasonable cost;
(b) The public welfare will be promoted by such additional
work;
(c) The cost of such additional work, when added to all expenses previously incurred by the district will not exceed the total
benefits theretofore assessed; and
(d) A petition, which is the same in substance or effect as the
current petition, has not previously been denied by the drainage
board.