Wisconsin Code § 295.62

Mining waste site construction and completion reports
Open in Lexace · Ask the AI about this section
(1) An operator shall construct a mining waste
site substantially in accordance with the approved mining waste
site feasibility study and plan of operation.
(2) The operator shall inspect the mining waste site before it
is used and ensure that all associated structures are in substantial
compliance with the mining waste site feasibility study and plan
of operation. The operator shall have a professional engineer,
registered as such under ch. 443, document mining waste site
construction and render an opinion as to whether the mining
waste site has been constructed in substantial conformance with
the mining waste site feasibility study and plan of operation. The
engineer may use aerial or ground photographs to document the
inspection, but photographs do not in themselves constitute compliance with this subsection. The operator shall maintain a complete file describing the items inspected and their condition.
(3) An operator shall notify the department in writing when
the mining waste site has been constructed in substantial compliance with the mining waste site feasibility study and plan of
operation.
(4) (a) Within 5 business days of receipt of written notice
from an operator that the mining waste site has been constructed
in substantial compliance with the mining waste site feasibility
study and plan of operation, the department shall either review
and inspect the mining waste site to ensure that it was constructed
according to the approved mining waste site feasibility study and
plan of operation or notify the operator that the department will
not conduct a review and inspection before disposal of mining
waste in the mining waste site. Within 3 business days of any review and inspection, the department shall notify the operator that
the mining waste site may be used for the disposal of mining
waste or identify all steps that must be completed to bring the
mining waste site into substantial compliance with the mining
waste site feasibility study and plan of operation. After the operator completes the steps, the operator shall notify the department
that the steps have been completed.
(b) An operator may dispose of mining waste in a mining
waste site after one of the following occurs:
1. The operator receives notice from the department under
par. (a) that the department will not conduct a review and inspection before disposal of mining waste in the mining waste site.
2. The operator receives notice from the department under
par. (a) that the mining waste site may be used for the disposal of
mining waste.
3. The operator provides notice to the department under par.
(a) that any steps required by the department to be completed under par. (a) have been completed.