But the lien created and authorized by section one of this article shall be discharged from
and after one hundred days from the completion of the contract and the lien created and
authorized by section two of this article shall be discharged from and after one hundred days
from the completion of the subcontract and the lien created and authorized by section three
of this article shall be discharged from and after one hundred days from thee furnishing of the
last of the materials, machinery or other supplies and equipment and the lien created and
authorized by section four of this article shall be discharged from and arfter one hundred
days from the date of the furnishing of the last of the materials, machinery or other
equipment or supplies and the lien created and authorized by section five of this article shall
be discharged from and after one hundred days from the date of the performing of the last of
the work and labor and the lien created and authorized by setction six of this article shall be
discharged from and after one hundred days from the date of the performing of the last of
the work and labor, unless, within the respective periods, the claimant of any such lien shall
have perfected and preserved the same, as hereinafter provided in this article.