West Virginia Code § 24-2-3a

Advance notice of filing of general rate case required
Open in Lexace · Ask the AI about this section
All public utilities subject to the provisions of section four or four-a of this article, intending
to institute a general rate case, shall give the commission not less than thirty days' notice
before proceeding under the provision of those sections unless the commission modifies or
waives such notice requirement.