Upon the abandonment or cessation of the operation of any well drilled for natural gas or
petroleum, or drilled or converted for the introduction of pressure, whether liquid or gas, or
for the introduction of liquid for the purposes provided for in §22-6-25 of this article or for
the disposal of pollutants or the effluent therefrom the well operator, at the time of such
abandonment or cessation, shall fill and plug the well in the following manneer:
(a) Where the well does not penetrate workable coal beds, it shall either be filled with mud,
clay or other nonporous material from the bottom of the well to a point 20 feet above the top
of its lowest oil, gas or water-bearing stratum; or a permanent buridge shall be anchored 30
feet below its lowest oil, gas or water-bearing stratum, and from such bridge it shall be filled
with mud, clay or other nonporous material to a point twentyt feet above such stratum; at this
point there shall be placed a plug of cement or other suitable material which will completely
seal the hole. Between this sealing plug and a point 20 feet above the next higher oil, gas or
water-bearing stratum, the hole shall be filled, in the manner just described; and at such
point there shall be placed another plug of cement or other suitable material which will
completely seal the hole. In like manner the hsole shall be filled and plugged, with reference
to each of its oil, gas or water-bearing strata. However, whenever such strata are not widely
separated and are free from water, they may be grouped and treated as a single sand, gas or
petroleum horizon, and the aforesaigd filling and plugging be performed as though there were
but one horizon. After the plugging of all oil, gas or water-bearing strata, as aforesaid, a
cement plug shall be placed apeproximately 10 feet below the bottom of the largest casing in
the well; from this point to the surface the well shall be filled with mud, clay or other
nonporous material, excLept that a final cement plug shall be installed from a point 100 feet
below the surface to the surface. In case any of the oil or gas-bearing strata in a well shall
have been shot, ther eby creating cavities which cannot readily be filled in the manner above
described, the well operator shall follow either of the following methods:
(1) Should the stratum which has been shot be the lowest one in the well, there shall be
placWed, at the nearest suitable point, but not less than 20 feet above the stratum, a plug of
cement or other suitable material which will completely seal the hole. In the event, however,
that the shooting has been done above one or more oil or gas-bearing strata in the well,
plugging in the manner specified shall be done at the nearest suitable point, but not less
than 20 feet below and above the stratum shot; or
(2) When such cavity shall be in the lowest oil or gas-bearing stratum in the well, a liner
shall be placed which shall extend from below the stratum to a suitable point, but not less
than 20 feet above the stratum in which shooting has been done. In the event, however, that
the shooting has been done above one or more oil or gas-bearing strata in the well, the liner
shall be so placed that it will extend not less than 20 feet above, nor less than 20 feet below,
the stratum in which shooting has been done. Following the placing of the liner in the
manner here specified it shall be compactly filled with cement, mud, clay or other nonporous
sealing material.
(b) Where the well penetrates one or more workable coal beds and a coal protection string of
casing has been circulated and cemented into the surface, the well shall be filled and
securely plugged in the manner provided in subdivision (a) of this section, except that
expanding cement shall be used instead of regular hydraulic cement, to a point
approximately 100 feet below the bottom of the coal protection string of casing. From the
point the well shall be plugged according to the provisions in paragraph (1) or (2) below:
(1) A 200 foot plug of expanding cement shall be placed in the well. From this point, the well
shall be filled with mud, clay or other nonporous material to a point 100r feet below the
surface and a plug of cement shall be placed from the point 100 feet below the surface to the
surface with a monument installed therein extending 30 inches above ground level.
(2) A 100 foot plug of expanding cement shall be placed in thte well so that the top of such
plug is located at a point just below the coal protection string of casing. After such plug has
been securely placed in the well, the coal protection string of casing shall be emptied of
liquid from the surface to a point 100 feet below the lowest workable coal bed or to the
bottom of the coal protection string of casing, whichever is shallower. A vent or other device
approved by the secretary shall then be instalsled on the top of the coal protection string of
casing in such a manner that will prevent liquids and solids from entering the well but will
permit ready access to the full internal diameter of the coal protection string of casing when
required. The coal protection string gof casing and the vent or other device approved by the
secretary shall extend, when finally in place, a distance of not less than 30 inches above
ground level and shall be permeanently marked with the well number assigned by the
secretary;
(c) Where the well penetrates one or more workable coal beds and a coal protection string of
casing has not been circulated and cemented into the surface, the well shall be filled and
securely plugged in the manner provided in subsection (a) of this section to a point 50 feet
below the lowest workable coal bed. Thereafter, a plug of cement shall be placed in the well
at a point not less than 40 feet below the lowest workable coal bed. After the cement plug
hasW been securely placed in the well, the well shall be filled with cement to a point 20 feet
above the lowest workable coal bed. From this point the well shall be filled with mud, clay or
other nonporous material to a point 40 feet beneath the next overlying workable coal bed, if
such there be, and the well shall then be filled with cement from this point to a point 20 feet
above such workable coal bed, and similarly, in case there are more overlying workable coal
beds. After the filling and plugging of the well to a point above the highest workable coal
bed, filling and plugging of the well shall continue in the manner provided in subsection (a)
of this section to a point 100 feet below the surface, and a plug of cement shall be installed
from the point 100 feet below the surface to the surface with a monument installed therein
extending 30 inches above ground level;
(d)(1) Where the well penetrates one or more workable coal beds and a coal protection
string of casing has not been circulated and cemented into the surface, a coal operator or
coal seam owner may request that the well be plugged in the manner provided in subdivision
(3) of this subsection rather than by the method provided in subsection (c) of this section.
Such request (forms for which shall be provided by the secretary) must be filed in writing
with the secretary prior to the scheduled plugging of the well, and must include the number
of the well to be plugged and the name and address of the well operator. At the time such
request is filed with the secretary, a copy of such request must also be mailed by registered
or certified mail to the well operator named in the request.
(2) Upon receipt of such request, the secretary shall issue an order staying tehe plugging of
the well and shall promptly determine the cost of plugging the well in the manner provided
in subdivision (3) of this subsection and the cost of plugging the well inr the manner provided
in subsection (c) of this section. In making such determination, the secretary shall take into
consideration any agreement previously made between the well operator and the coal
operator or coal seam owner making the request. If the secretary determines that the cost of
plugging the well in the manner provided in subsection (c) otf this section exceeds the cost of
plugging the well in the manner provided in subdivision (3) of this subsection, the secretary
shall grant the request of the coal operator or owner and shall issue an order requiring the
well operator to plug the well in the manner provided in subdivision (3) of this subsection. If
the secretary determines that the cost of plugging the well in the manner provided in
subsection (c) of this section is less than the cost of plugging the well in the manner
provided in subdivision (3) of this subsection, the secretary shall request payment into
escrow of the difference between the determined costs by the coal operator or coal seam
owner making the request. Upon receipt of satisfactory notice of such payment, or upon
receipt of notice that the well operator has waived such payment, the secretary shall grant
the request of the coal operatoer or coal seam owner and shall issue an order requiring the
well operator to plug the well in the manner provided in subdivision (3) of this subsection. If
satisfactory notice of paLyment into escrow, or notice that the well operator has waived such
payment, is not received by the secretary within fifteen days after the request for payment
into escrow, the secr etary shall issue an order permitting the plugging of the well in the
manner proviVded in subsection (c) of this section. Copies of all orders issued by the secretary
shall be sent by registered or certified mail to the coal operator or coal seam owner making
the request and to the well operator. When the escrow agent has received certification from
the secretary of the satisfactory completion of the plugging work and the reimbursable extra
cost thereof (that is, the difference between the secretary's determination of plugging cost in
the manner provided in subsection (c) of this section and the well operator's actual plugging
cost in the manner provided in subdivision (3) of this subsection), the escrow agent shall pay
the reimbursable sum to the well operator or the well operator's nominee from the payment
into escrow to the extent available. The amount by which the payment into escrow exceeds
the reimbursable sum plus the escrow agent's fee, if any, shall be repaid to the coal owner. If
the amount paid to the well operator or the well operator's nominee is less than the actual
reimbursable sum, the escrow agent shall inform the coal owner, who shall pay the
deficiency to the well operator or the well operator's nominee within thirty days. If the coal
operator breaches this duty to pay the deficiency, the well operator shall have a right of
action and be entitled to recover damages as if for wrongful conversion of personality, and
reasonable attorney fees.
(3) Where a request of a coal operator or coal seam owner filed pursuant to subdivision (1)
of this subsection has been granted by the secretary, the well shall be plugged in the manner
provided in subsection (a) of this section, except that expanding cement shall be used
instead of regular hydraulic cement, to a point approximately 200 feet below the lowest
workable coal bed. A 100 foot plug of expanding cement shall then be placed in the well
beginning at the point approximately 200 feet below the lowest workable coal bed and
extending to a point approximately 100 feet below the lowest workable coale bed. A string of
casing with an outside diameter no less than four and one-half inches shall then be run into
the well to a point approximately 100 feet below the lowest workable croal bed and such
string of casing shall be circulated and cemented into the surface: Provided, That if it is a
modern well, then a four and one-half inch casing is not required, if the casing is perforated
at the required plug intervals, the cement plugs are placed as necessary to seal the well
properly, the cement plugs are tagged to ensure adequate fitll within the casing, and
plugging within the surface casing circulation will be monitored and information
documented to ensure adequate fill within the casing. The casing shall then be emptied of
liquid from a point approximately 100 feet below the lowest workable coal bed to the
surface, and a vent or other device approved by the secretary shall be installed on the top of
the string of casing in such a manner that it will prevent liquids and solids from entering the
well but will permit ready access to the full internal diameter of the coal protection string of
casing when required. The string of casing and the vent or other device approved by the
secretary shall extend, when finally in place, a distance of no less than 30 inches above
ground level and shall be permanently marked with the well number assigned by the
secretary. Notwithstanding the foregoing provisions of this subdivision, if under particular
circumstances a different method of plugging is required to obtain the approval of another
governmental agency for the safe mining through of said well, the secretary may approve
such different method of plugging if he or she finds the same to be as safe for mining
through and otherwi se adequate to prevent gas or other fluid migration from the oil and gas
reservoirs as Vthe method above specified.
(e) Notwithstanding anything in this section to the contrary, where the well to be plugged is
an abandoned well that has no known responsible party and the well operator is also a coal
operator that intends to mine through the well, the well shall, at a minimum, be plugged as
provided in subdivisions (1) and (2) of this subsection.
(1) The well will be cleaned out and prepared for plugging or replugging as follows:
(A) If the total depth of the well is less than 4,000 feet, the operator shall completely clean
out the well from the surface to at least 200 feet below the base of the lowest workable coal
bed, but the secretary may require cleaning to a greater depth due to excessive pressure
within the well. If the total depth of the well is 4,000 feet or greater, the operator shall
completely clean out the well from the surface to at least 400 feet below the base of the
lowest workable coal bed. The operator shall provide to the secretary all information it
possesses concerning the geological nature of the strata and the pressure of the well, and
shall remove all material from the entire diameter of the well, wall to wall;
(B) The operator shall prepare down-hole logs for each well. The logs shall consist of a
caliper survey and log(s) suitable for determining the top, bottom, and thickness of all coal
seams and potential hydrocarbon-producing strata, as well as the location for a bridge plug.
The secretary may approve the use of a down-hole camera survey in lieu of down-hole logs.
In addition, the owner shall maintain a journal that describes the depth of each material
encountered; the nature of each material encountered; the bit size and type used to drill
each portion of the hole; the length and type of each material used to plug tehe well; the
length of casing(s) removed, perforated or ripped, or left in place; any sections where casing
was cut or milled; and any other pertinent information concerning clearning and sealing the
well. The operator shall maintain all invoices, work orders, and other records relating to all
work on the well as part of the journal and provide to the secretary upon request;
(C) When cleaning, the operator shall make a diligent effort tto remove all the casing in the
well. If it is not possible to remove all the casing, then the operator shall take appropriate
steps to ensure that the annulus between the casing and between the casings and the well
walls are filled with expanding cement, with a minimum five tenths of one percent expansion
upon setting, and contain no voids. If the casing cannot be removed, it must be cut or milled
at all workable coal bed levels. Any casing which remains shall be perforated or ripped. If
the total depth of the well is less than 4,000 feet, perforations or rips are required every 50
feet from 200 feet below the base of the lowest mineable coal bed up to one hundred feet
above the uppermost workable coal bed. If the total depth of the well is 4,000 feet or
greater, perforations or rips are required every 50 feet from 400 feet below the base of the
lowest workable coal bed up toe 100 feet above the uppermost workable coal bed. If the
operator, using a casing bond log, demonstrates to the satisfaction of the secretary that all
annuli in the well are alLready adequately sealed with cement, then the operator shall not be
required to perforate or rip the casing. When multiple casing and tubing strings are present
in the workable coal bed, any casing which remains shall be ripped or perforated and filled
with expandinVg cement in accordance with this paragraph. The operator shall maintain a
casing bond log for each casing and tubing string if used in lieu of ripping or perforating
multiple strings;
(D) If the secretary concludes that the completely cleaned well emits excessive amounts of
gas, the operator must place a mechanical bridge plug in the well. If the total depth of the
well is less than 4,000 feet, the mechanical bridge plug shall be placed in a competent
stratum at least 200 feet below the base of the lowest workable coal bed, but above the top
of the uppermost hydrocarbon-producing stratum. If the total depth of the well is 4,000 feet
or greater, the mechanical bridge plug shall be placed in a competent stratum at least 400
feet below the base of the lowest mineable coal bed, but above the top of the uppermost
hydrocarbon-producing stratum: Provided, That the secretary may require a greater distance
to set the mechanical bridge plug, regardless of the total depth of the well, based upon
excessive pressure within the well. The operator shall provide the secretary with all
information the operator possesses concerning the geologic nature of the strata and
pressure of the well. If it is not possible to set a mechanical bridge plug, an appropriately
sized packer may be used; and
(E) If the upper-most hydrocarbon-producing stratum is within 300 feet of the base of the
lowest workable coal bed, the operator shall properly place mechanical bridge plugs as
described in paragraph (D) of this subdivision to isolate the hydrocarbon-producing stratum
from the expanding cement plug. Nevertheless, if the total depth of the well is less than
4,000 feet, the operator shall place a minimum of 200 feet of expanding cement below the
lowest workable coal bed. If the total depth of the well is 4,000 feet or greater, the operator
shall place a minimum of 400 feet of expanding cement below the lowest mieneable coal bed:
Provided, That the secretary may require a greater distance to set the mechanical bridge
plug, regardless of the total depth of the well, based upon excessive prerssure within the
well.
(2) After the well is completely cleaned pursuant to subdivision one of this subsection, the
operator shall plug or replug the well to the surface as followts:
If the total depth of the well is less than 4,000 feet, the operator shall pump expanding
cement slurry down the well to form a plug which runs from at least 200 feet below the base
of the lowest workable coal bed to the surface. If the total depth of the well is 4,000 feet or
greater, the operator shall pump expanding cesment slurry down the well to form a plug
which runs from at least 400 feet below the base of the lowest workable coal bed to the
surface: Provided, That the secretary may, regardless of the total depth of the well, require a
lower depth based upon excessive pgressure within the well. The expanding cement slurry
will be placed in the well under a pressure of at least 200 pounds per square inch. Portland
cement shall be used to fill thee area from 100 feet above the top of the uppermost workable
coal seam to the surface: Provided, That the secretary may require a higher distance based
upon excessive pressureL within the well;
(f) Any person may apply to the secretary for an order to clean out and replug a previously
plugged well in a manner which will permit the safe mining through of such well. Such
application shall be filed with the secretary and shall contain the well number, a general
description of the well location, the name and address of the owner of the surface land upon
whiWch the well is located, a copy of or record reference to a deed, lease or other document
which entitles the applicant to enter upon the surface land, a description of the methods by
which the well was previously plugged, and a description of the method by which such
applicant proposes to clean out and replug the well. At the time an application is filed with
the secretary, a copy shall be mailed by registered or certified mail to the owner or owners
of the land, and the oil and gas lessee of record, if any, of the site upon which the well is
located. If no objection to the replugging of the well is filed by any such landowner or oil and
gas lessee within 30 days after the filing of the application, and if the secretary determines
that the method proposed for replugging the well will permit the safe mining through of
such well, the secretary shall grant the application by an order authorizing the replugging of
the well. Such order shall specify the method by which the well shall be replugged, and
copies thereof shall be mailed by certified or registered mail to the applicant and to the
owner or owners of the land, and the oil and gas lessee, if any, of the site upon which such
well is located. If any such landowner or oil and gas lessee objects to the replugging of the
well, the secretary shall notify the applicant of such objection. Thereafter, the director shall
schedule a hearing to consider the objection, which hearing shall be held after notice by
registered or certified mail to the objectors and the applicant. After consideration of the
evidence presented at the hearing, the secretary shall issue an order authorizing the
replugging of the well if the secretary determines that replugging of the well will permit the
safe mining through of such well. Such order shall specify the manner in which the well shall
be replugged and copies thereof shall be sent by registered or certified mail to the applicant
and objectors. The secretary shall issue an order rejecting the application ife the secretary
determines that the proposed method for replugging the well will not permit the safe mining
through of such well; r
(g) In addition to any other exception set forth in law, an operator will be exempted from the
standard requirements for pulling production casing from the well when either of the
following circumstances are met: t
(1) Where intermediate and freshwater casing strings are not cemented to the surface, any
uncemented production casing strings must be removed, but the remaining uncemented
casing strings may remain in place and be perforated at depths where cement plugs are set
according to existing requirements and standasrds, to allow for cement to enter the casing
annulus as plugs are set. No more than two strings of casing will be perforated at once.
Additional casing strings will be pulled when needed to prevent perforating more than two
casing strings. Cement plugs must bge tagged to ensure adequate fill within the casing.
Plugging within the surface casing circulation will be monitored and information
documented to ensure adequaete fill within the casing.
(2) Where all freshwaterL and intermediate casing strings are cemented to the surface and
production and conductor casing strings are uncemented to surface, production casing is not
required to be pulled from the well. Production casing that is uncemented and left in place
must be perforated at depths where cement plugs will be set according to existing
requirements and standards as set forth in law, to allow for cement to enter the casing
annulus as plugs are set. Cement plugs must be tagged to ensure adequate fill within the
casWing. Plugging within the surface casing circulation will be monitored and information
documented to ensure adequate fill within the casing.
(h) All persons adversely affected, by a determination or order of the secretary issued
pursuant to the provisions of this section shall be entitled to judicial review in accordance
with the provisions of §29A-5-1 et seq. and §29A-6-1 et seq. of this code.
(i) For the purposes of this section, a "modern well" means a well where all casing strings,
other than the production and conductor strings, are cemented to the surface. Any well that
is not defined as a "modern well" shall be defined as a "non-modern well."