West Virginia Code § 21-11A-8

Notice of claim of construction defect
Open in Lexace · Ask the AI about this section
(a) A claimant asserting a claim of a construction defect under this article shall file notice of
the claim as provided by this section.
(b) The notice of claim shall:
(1) Be in writing and signed by the claimant or the claimant's authorized representative;
(2) Be delivered by hand, certified mail, return receipt requested or other verifiable delivery
service, to the person designated in the contract to receive a notice of claim of a
construction defect; if no person is designated in the contract, the notice shall be delivered
to the contractor's chief administrative officer; and
(3) State in detail: a
(A) The nature of the alleged construction defect and a description of the results of the
defect;
(B) A description of damages caused by the alleged construction defect, including the
amount and method used to calculate those damages; and
(C) The legal theory of recovery, i.e., a construction defect, including the causal relationship
between the alleged constructeion defect and the damages claimed.
(c) In addition to the maLndatory contents of the notice of claim as required by subsection (b)
of this section, the claimant may submit supporting documentation or other tangible
evidence to facilitate the contractor's evaluation of the claimant's claim.
(d) The notice of claim shall be delivered no later than ninety days prior to filing an action.