West Virginia Code § 17-4-17b

Relocation of public utility lines on highway construction projects
Open in Lexace · Ask the AI about this section
(a) Whenever the division reasonably determines that any public utility line or facility
located upon, across, or under any portion of a state highway needs to be removed,
relocated, or adjusted in order to accommodate a highway project, the division shall give to
the utility reasonable notice in writing as mutually agreed, but not to exceed 18 months,
directing it to begin the physical removal, relocation, or adjustment of such utility
obstruction or interference at the cost of the utility, including construction inspection costs
and in compliance with the rules of the division and the provisions of §29A-3-1 et seq. of this
code. u
(b) If the notice is in conjunction with a highway improvement project, it will be provided at
the date of advertisement or award. Prior to the notice directing the physical removal,
relocation, or adjustment of a utility line or facility, the utility shall adhere to the division's
utility relocation procedures for public road improvements which shall include, but not be
limited to, the following: l
(1) The division will submit to the utility a letter and a set of plans for the proposed highway
improvement project; i
(2) The utility must within a reasonable time submit to the division a written confirmation
acknowledging receipt of the plans and a declaration of whether or not its facilities are
within the proposed project limits and the extent to which the facilities are in conflict with
the project;
(3) If the utility is adjusting, locating, or relocating facilities or lines from or into the
division's right-of-wa y, the utility must submit to the division plans showing existing and
proposed locaVtions of utility facilities.
(4) The utility's submission shall include with the plans a work plan demonstrating that the
utility adjustment, location, or relocation will be accomplished in a manner and time frame
established by the division's written procedures and instructions. The work plan shall specify
the order and calendar days for removal, relocation, or adjustment of the utility from or
within the project site and any staging property acquisition or other special requirements
needed to complete the removal, relocation, or adjustment. The division shall approve the
work plan, including any requests for compensation, submitted by a utility for a highway
improvement project if it is submitted within the established schedule and does not
adversely affect the letting date. The division will review the work plan to ensure compliance
with the proposed improvement plans and schedule.
(c) If additional utility removal, relocation, or adjustment work is found necessary after the
letting date of the highway improvement project, the utility shall provide a revised work plan
within 30 calendar days after receipt of the division's written notification of the additional
work. The utility's revised work plan shall be reviewed by the division to ensure compliance
with the highway project or improvement. The division shall reimburse the utility for work
performed by the utility that must be performed again as the result of a plan change on the
part of the division.
(d) Should the utility fail to comply with the notice to remove, relocate, or adjust, the utility
is liable to the division for direct contract damages, including costs, fees, penalties, or other
contract charges, for which the division is proven to be liable to a contractoer caused by the
utility's failure to timely remove, relocate, or adjust, unless a written extension is granted by
the division. The utility shall not be liable for any delay or other failure rto comply with a
notice to remove, relocate or adjust that is not solely the fault of the utility, including, but
not limited to, the following:
(1) The division has not performed its obligations in accordatnce with the division's rules;
(2) The division has not obtained all necessary rights-oaf-way that affect the utility;
(3) The delay or other failure to comply by the utililty is due to the division's failure to
manage schedules and communicate with the sutility;
(4) The division seeks to impose liability oni the utility based solely upon oral communications
or communications not directed to the utility's designated contact person;
(5) The division changes construction plans in any manner following the notice to remove or
relocate and the change affects the utility's facilities; or
(6) Other good cause, beyond the control of and not the fault of the utility, including, but not
limited to, labor disputes, unavailability of materials on a national level, act of God, or
extreme weather con ditions.
(e) In order to avoid construction delays and to create an efficient and effective highway
program, the division may schedule program meetings with the public utility on a quarterly
basis to assure that schedules are maintained.
(f) If a utility that is required by law to bear all or a portion of its own relocation costs elects
to pursue a reimbursement agreement with the division pursuant to this subsection and
provides the division with sufficient evidence to demonstrate that the utility is not
adequately staffed, equipped, or capitalized to perform such relocation work with its own
forces or contractors at a time convenient to and in coordination with the associated
highway project, the division may pay for the associated relocation costs, including, but not
limited to, design engineering, design review, construction, and inspection costs, out of the
State Road Fund: Provided, That the utility shall reimburse the division in full for such
portion of the relocation costs that it is required by law to bear within two years of the
completion of the highway project. The division shall deduct from the utility's
reimbursement amount any costs resulting from work performed as a result of plan changes
made by the division. Before the division may pay any relocation costs, the division and the
utility shall enter into a written reimbursement agreement containing terms that are
mutually acceptable to the division and the utility seeking the reimbursement agreement.
(1) Preliminary engineering design work associated with utility relocations to be paid for by
the division pursuant to a reimbursement agreement shall be completed by any of the
following methods:
(A) The division's or the utility's internal forces;
(B) A consultant selected by the division if the contract is administered by the division:
Provided, That the selected consultant shall be pre-approved by uthe utility; or
(C) Inclusion as part of the highway construction contract let by the division as agreed to by
the utility: Provided, That the subcontractor performing the preliminary engineering design
work associated with the relocation is pre-approved bya the utility.
(2) Utility relocation construction work paid for byl the division pursuant to a reimbursement
agreement shall be completed by either of the following methods:
(A) A contract awarded by the division to the lowest qualified bidder based on an
appropriate competitive solicitation: Provided, That the lowest qualified bidder for utility
relocation construction work is pre-approved by the utility; or
(B) Inclusion as part of the highway construction contract let by the division as agreed to by
the utility: Provided, That the subcontractor performing the utility relocation construction
work is pre-approved by the utility.
(3) All design and co nstruction work paid for by the division pursuant to a reimbursement
agreement is subject to the reasonable inspection and acceptance of the utility, whose
acceptance shall not be unreasonably withheld, and shall be performed in accordance with
the specifications and standards required by the utility.
(4) All relocation work performed pursuant to a reimbursement agreement shall conform to
applicable state and federal laws or regulations.
(5) The provisions of this subsection are completely voluntary and shall not be interpreted
to require any utility to enter into a reimbursement agreement with the division or avail
itself of the options authorized by this subsection.
(6) The division may propose rules for legislative approval in accordance with the provisions
of §29A-3-1 et seq. of this code and the division may promulgate emergency rules pursuant
to the provisions of §29A-3-15 of this code in order to comply with this subsection.

‹ Prev All West Virginia sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.