Washington Code § 82.89.050

Requirements for recipients—Meaningful construction
Open in Lexace · Ask the AI about this section
(1) The recipient of a deferral certificate under RCW 82.89.040 must begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate unless construction was delayed due to circumstances beyond the recipient's control. Lack of funding is not considered a circumstance beyond the recipient's control. (2) If the recipient does not begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, the deferral certificate issued under RCW 82.89.040 is invalid and taxes deferred under this chapter are due immediately.