(1) The legislature finds that the construction of hydraulic projects may require mitigation for the protection of fish life, and that the mitigation may be most cost-effective and provide the most benefit to the fish resource if the mitigation is allowed to be applied in locations that are off-site of the hydraulic project location. The department may approve off-site mitigation plans that are submitted by permit applicants. (2) If a permit applicant proposes off-site mitigation and the department does not approve the permit or conditions the permit in such a manner as to render off-site mitigation unpracticable, the project proponent may appeal the decision as provided in *RCW 77.55.021(4).