Virginia Code § 56-596.5

Rate increases in certain months prohibited; Phase I Utility
Open in Lexace · Ask the AI about this section
A. Notwithstanding any other provision of law, the rates for electric generation and distribution services by a Phase I Utility, as defined in subdivision A 1 of § 56-585.1, shall not be increased during the months of November through February.
B. Notwithstanding any other provision of law, during the months of November through February, no new rate adjustment clause shall be applied to a Phase I Utility's residential customers' bills and no existing rate adjustment clause applicable to such customers' bills shall be increased. The Commission's final order regarding any petition for a rate adjustment clause that results in an increase to residential customer rates, including any petition filed pursuant to subdivision A 4, 5, or 6 of § 56-585.1 or § 56-585.1:15, 56-585.5, or 56-585.6, issued between September 1 and December 31 shall direct that the applicable rate adjustment clause be applied to customers' bills beginning on March 1 of the following year.
2025, cc. 497, 597.

‹ Prev All Virginia sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.