Utah Code § 72-6-107

Construction or improvement of highway -- Contracts -- Retainage -- Certain
Open in Lexace · Ask the AI about this section
indemnification provisions forbidden.
(1) As used in this section, "design professional" means:
(a) an architect, licensed under Title 58, Chapter 3a, Architects Licensing Act;
(b) a landscape architect, licensed under Title 58, Chapter 53, Landscape Architects Licensing
Act; and
(c) a professional engineer or professional land surveyor, licensed under Title 58, Chapter 22,
Professional Engineers and Professional Land Surveyors Licensing Act.
(2)
(a) The department shall make plans, specifications, and estimates prior to the construction or
improvement of any state highway.
(b) Except as provided in Section 63G-6a-1402 and except for construction or improvements
performed with state prison labor, a construction or improvement project with an estimated
cost exceeding the bid limit as defined in Section 72-6-109 for labor and materials shall be
performed under contract awarded to the lowest responsible bidder.
(c)
(i) The department:
(A) shall publish an advertisement for bids in accordance with Section 45-1-101, for a period
of two weeks ending no more than 10 days before bids are opened; and
(B) may publish an advertisement for bids in a newspaper of general circulation in the county
in which the work is to be performed.
(ii) If the department publishes an advertisement for bids in a newspaper under Subsection
(2)(c)(i)(B), the department shall publish the advertisement at least once a week for two
consecutive weeks, with the last publication at least 10 days before bids are opened.
(d) The department shall receive sealed bids and open the bids at the time and place designated
in the advertisement. The department may then award the contract but may reject any and all
bids.
(e) If the department's estimates are substantially lower than any responsible bid received, the
department may perform any work by force account.
(3) If any payment on a contract with a private contractor for construction or improvement of a state
highway is retained or withheld, the payment shall be retained or withheld and released as
provided in Section 13-8-5.
(4) If the department performs a construction or improvement project by force account, the
department shall:

(a) provide an accounting of the costs and expenditures of the improvement including material
and labor;
(b) disclose the costs and expenditures to any person upon request and allow the person to
make a copy and pay for the actual cost of the copy; and
(c) perform the work using the same specifications and standards that would apply to a private
contractor.
(5) In accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act, the department
shall establish procedures for:
(a) hearing evidence that a region within the department violated this section; and
(b) administering sanctions against the region if the region is found in violation.
(6)
(a) Beginning May 12, 2009, a contract, including an amendment to an existing contract, entered
into under authority of this chapter may not require that a design professional indemnify
another from liability claims that arise out of the design professional's services, unless
the liability claim arises from the design professional's negligent act, wrongful act, error or
omission, or other liability imposed by law.
(b) Subsection (6)(a) may not be waived by contract.
(c) Notwithstanding Subsections (6)(a) and (b), a design professional may be required to
indemnify a person for whom the design professional has direct or indirect control or
responsibility.

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.