A large load customer shall pay all just and reasonable large load incremental costs necessary to receive electric service, including the costs of: (1) generation resources; (2) distribution system upgrades; (3) to the extent permitted by federal law, and, as applicable, approved by the Federal Energy Regulatory Commission: (a) transmission system improvements, including network upgrades; and (b) interconnection facilities; (4) transmission service; and (5) other necessary infrastructure.