Utah Code § 54-18-201

Public utility to obtain approval for high voltage power lines
Open in Lexace · Ask the AI about this section
(1) Except as provided in Subsections (2) and (3), a public utility shall comply with the
requirements of this chapter before beginning construction or operation of:
(a) a high voltage power line; or
(b) an upgraded high voltage power line.

(2) A public utility is not subject to the provisions of this chapter if the public utility has on or before
May 12, 2009:
(a) filed an application for or obtained a certificate of convenience and necessity for a high
voltage power line in accordance with the provisions of Section 54-4-25; or
(b) has initiated the acquisition of right-of-way for the construction of the high voltage
transmission line.
(3) A transmission line that is subject to federal permitting is not subject to the provisions of this