(1) As used in this part:
(a) "Baseload capacity" means the amount of baseload power that electricity generation
resources can reliably produce through continuous or nearly continuous operation.
(b) "Baseload electricity resource" means an electricity generation resource that operates
continuously or nearly continuously to maintain a stable power supply at the electricity
generation resource's rated capacity.
(c) "Baseload power" means the minimum amount of electric power continuously needed to meet
basic system demand.
(d) "Demand management program" means any incentive or technology designed to modify the
timing or amount of customer electricity consumption.
(e) "Expected deliverable energy" means the amount of electrical energy that a resource can
reliably deliver to the grid based on historical performance data and operational constraints.
(f) "Firming capacity" means the amount of electric power that electricity generation resources
can produce, at the system operator's discretion, to reliably meet peak load and balance
fluctuations in electrical demand or supply.
(g) "Plant factor" means the same as that term is defined in Section 79-6-303.
(h) "Resource adequacy program" means a program that establishes capacity contribution values
for generation resources based on historical performance data.
(i)
(i) "Supplemental resource" means a utility asset or operational control required to maintain
reliable power delivery when a variable energy resource is not operating at full capacity.
(ii) "Supplemental resource" includes:
(A) generation resources;

(B) transmission resources;
(C) energy balancing measures; and
(D) market purchases.
(j) "Variable capacity" means the amount of electric power that electricity generation resources
can produce when operating on a variable basis due to elements outside of operator control.
(k) "Variable energy resource" means an electricity generation facility that cannot consistently
deliver power at the facility's rated capacity due to elements outside of the operator's control.
(l) "Voluntary conservation program" means a program that:
(i) provides customers financial incentives or cost-saving opportunities to reduce energy
consumption;
(ii) maintains the customer's control over the customer's energy usage decisions; and
(iii) allows customers to opt out of any offered programs without restrictive penalties or length
commitments.
(2) An affected electrical utility shall file with the commission any action plan developed as part of
the affected electrical utility's integrated resource plan to enable the commission to review and
provide guidance to the affected electrical utility.
(3) An affected electrical utility's action plan shall:
(a) report baseload energy resources as baseload capacity, specifying the expected deliverable
energy;
(b) report variable energy resources as variable capacity, specifying the expected deliverable
energy;
(c) report energy storage systems, including batteries and other storage devices, as firming
capacity;
(d) report variable energy resources paired with energy storage as firming capacity, subject to the
energy storage system requirements in Subsection (3)(g)(ii);
(e) separately report any expected curtailment of baseload and variable energy resources
resulting from regulations, costs, or demand constraints; and
(f) attribute relevant costs of supplemental resources to the variable energy resources that
necessitate the use of supplemental resources;
(g) for generation capacity calculations:
(i) exclude energy conservation measures and demand reduction programs;
(ii) reflect actual delivery capability for energy storage systems, accounting for:
(A) charging requirements;
(B) duration limitations; and
(C) seasonal performance variations in capacity and duration; and
(iii) for variable energy resources, use:
(A) capacity assumptions for long-term planning; and
(B) capacity and plant factor values established by a resource adequacy program in which the
affected electrical utility's resource adequacy participates.
(4)
(a) In accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act, the
commission shall make rules providing a process for its review of an action plan.
(b) The rules required under Subsection (4)(a) shall provide sufficient flexibility to permit changes
in an action plan between the periodic filings of the affected electrical utility's integrated
resource plan.

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.