Utah Code § 54-14-303

Actions or disputes for which board review may be sought
Open in Lexace · Ask the AI about this section
(1) A local government or public utility may seek review by the board, if:
(a) a local government has imposed requirements on the construction of a facility that result in
estimated excess costs without entering into an agreement with the public utility to pay for
the actual excess cost, except any actual excess costs specified in Subsection 54-14-201(2)
(a) or (2)(b), at least 30 days before the date construction of the facility should commence in
order to avoid significant risk of impairment of safe, reliable, efficient, and adequate service to
customers of the public utility;
(b) there is a dispute regarding:
(i) the estimated excess cost or standard cost of a facility;
(ii) when construction of a facility should commence in order to avoid significant risk of
impairment of safe, reliable, and adequate service to customers of the public utility;
(iii) whether the public utility has sought a permit, authorization, approval, exception, or waiver
with respect to a facility sufficiently in advance of the date construction should commence,
based upon reasonably foreseeable conditions, to allow the local government reasonable
time to pay for any estimated excess cost;
(iv) the geographic boundaries of a proposed corridor as set forth in a notice submitted by a
public utility to a local government pursuant to the provisions of Subsection 54-18-301(2)
(a), provided the action is filed by the local government before the public utility files an
application for a land use permit as set forth in Subsection 54-18-304(1)(a); or
(v) a modification proposed by a local government to a utility's proposed corridor that is
identified in the public utility's notice of intent required pursuant to Subsection 54-18-301(3);
(c) a local government has required construction of a facility in a manner that will not permit the
utility to provide service to its customers in a safe, reliable, adequate, or efficient manner;
(d) a local government has prohibited construction of a facility which is needed to provide safe,
reliable, adequate, and efficient service to the customers of the public utility;
(e) a local government has not made a final decision on the public utility's application for a permit,
authorization, approval, exception, or waiver with respect to a facility within 60 days of the
date the public utility applied to the local government for the permit, authorization, approval,
exception, or waiver;
(f) a facility is located or proposed to be located in more than one local government jurisdiction
and the decisions of the local governments regarding the facility are inconsistent; or
(g) a facility is proposed to be located within a local government jurisdiction to serve customers
exclusively outside the jurisdiction of the local government and there is a dispute regarding
the apportionment of the actual excess cost of the facility between the local government and
the public utility.
(2)
(a) If an action is filed by a local government pursuant to Subsection (1)(b)(iv) or (v) seeking
a modification to a target study area or a proposed corridor, the local government shall
provide written notice of the action to any potentially affected landowner, as defined in Section
54-18-102, or affected entity, as defined in Section 54-18-102.
(b) A potentially affected landowner, as defined in Section 54-18-102, or affected entity, as
defined in Section 54-18-102, shall have a right to intervene as a party in the proceeding.

‹ Prev All Utah sections Next ›