Utah Code § 54-14-203

Actual excess cost
Open in Lexace · Ask the AI about this section
(1) If a local government issues a permit, authorization, approval, exception, or waiver based upon
its agreement to pay for the actual excess cost of a facility, the local government shall within 30
days either accept the estimate of excess cost as the actual excess cost of a facility or request
the public utility to obtain competitive bids for the facility if constructed in accordance with the
requirements and conditions of the local government.
(2) If the local government requests the public utility to obtain competitive bids, the public
utility shall obtain competitive bids, and the actual excess cost of the facility shall be the
difference between the lowest bid acceptable to the public utility plus the public utility's contract
administration and oversight expense and the standard cost of the facility.
(3) Any dispute regarding specifications, lowest acceptable bid, or administration and oversight
expense shall be resolved by the board on an expedited basis.

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.