Utah Code § 38-1a-506

Notice of intent to obtain final completion
Open in Lexace · Ask the AI about this section
(1) An owner of a nonresidential construction project that is registered with the registry, or an
original contractor of a commercial nonresidential construction project that is registered with
the registry under Section 38-1a-501, shall file with the registry a notice of intent to obtain final
completion as provided in this section if:
(a) the completion of performance time under the original contract for construction work is greater
than 120 days;
(b) the total original construction contract price exceeds $500,000; and
(c) the original contractor or owner has not obtained a payment bond in accordance with Section
14-2-1.
(2) The notice of intent described in Subsection (1) shall be filed at least 45 days before the day on
which the owner or original contractor of a commercial nonresidential construction project files
or could have filed a notice of completion under Section 38-1a-507.
(3) A person who provides construction work to an owner or original contractor who files a notice
of intent in accordance with Subsection (1) shall file an amendment to the person's preliminary
notice previously filed by the person as required in Section 38-1a-501:
(a) that includes:
(i) a good faith estimate of the total amount remaining due to complete the contract, purchase
order, or agreement relating to the person's approved construction work;
(ii) the identification of each original contractor or subcontractor with whom the person has a
contract or contracts for providing construction work; and
(iii) a separate statement of all known amounts or categories of work in dispute; and
(b) no later than 20 days after the day on which the owner or original contractor files a notice of
intent.
(4)
(a) A person described in Subsection (3) may demand a statement of adequate assurance
from the owner, original contractor, or subcontractor with whom the person has privity of
contract no later than 10 days after the day on which the person files a balance statement in
accordance with Subsection (3) from an owner, original contractor, or subcontractor who is in
privity of contract with the person.
(b) A demand for adequate assurance as described in Subsection (4)(a) may include a request
for a statement from the owner, original contractor, or subcontractor that the owner, original
contractor, or subcontractor has sufficient funds dedicated and available to pay for all sums
due to the person filing for the adequate assurances or that will become due in order to
complete a construction project.
(c) A person who demands adequate assurance under Subsection (4)(a) shall deliver copies of
the demand to the owner and original contractor:
(i) by hand delivery with a responsible party's acknowledgment of receipt;
(ii) by certified mail with a return receipt; or
(iii) as provided under Rule 4, Utah Rules of Civil Procedure.
(5)
(a) A person described in Subsection (3) may bring a legal action against a party with whom
the person is in privity of contract, including a request for injunctive or declaratory relief, to

determine the adequacy of the funds of the owner, original contractor, or subcontractor with
whom the demanding person contracted if, after the person demands adequate assurance in
accordance with the requirements of this section:
(i) the owner, original contractor, or subcontractor fails to provide adequate assurance that
the owner, original contractor, or subcontractor has sufficient available funds, or access
to financing or other sufficient available funds, to pay for the completion of the demanding
person's approved work on the construction project; or
(ii) the parties disagree, in good faith, as to whether there are adequate funds, or access to
financing or other sufficient available funds, to pay for the completion of the demanding
person's approved work on the construction project.
(b) If a court finds that an owner, original contractor, or subcontractor has failed to provide
adequate assurance in accordance with Subsection (4)(a), the court may require the owner,
original contractor, or subcontractor to post adequate security with the court sufficient to
assure timely payment of the remaining contract balance for the approved work of the person
seeking adequate assurance, including:
(i) cash;
(ii) a bond;
(iii) an irrevocable letter of credit;
(iv) property;
(v) financing; or
(vi) another form of security approved by the court.
(6)
(a) A person is subject to the civil penalty described in Subsection (6)(b), if the person files a
balance statement described in Subsection (3) that misrepresents the amount due under the
contract with the intent to:
(i) charge an owner, original contractor, or subcontractor more than the actual amount due; or
(ii) procure any other unfair advantage or benefit on the person's behalf.
(b) The civil penalty described in Subsection (6)(a) is the greater of:
(i) twice the amount by which the balance statement filed under Subsection (3) exceeds the
amount actually remaining due under the contract for completion of construction; and
(ii) the actual damages incurred by the owner, original contractor, or subcontractor.
(7) A court shall award reasonable attorney fees to a prevailing party for an action brought under
this section.
(8) Failure to comply with the requirements established in this section does not affect any other
requirement or right under this chapter.
(9) A person who has not filed a preliminary notice as required under Section 38-1a-501 is not
entitled to a right or a remedy provided in this section.
(10) This section does not create a cause of action against a person with whom the demanding
party is not in privity of contract.

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.