Utah Code § 38-1a-503

Relation back and priority of liens
Open in Lexace · Ask the AI about this section
(1) A construction lien relates back to, and takes effect as of, the time of the first preliminary notice
filing.
(2)
(a) Subject to Subsection (2)(b), a construction lien has priority over:
(i) any lien, mortgage, or other encumbrance that attaches after the first preliminary notice filing;
and
(ii) any lien, mortgage, or other encumbrance of which the claimant had no notice and which
was unrecorded at the time of the first preliminary notice filing.
(b) A recorded mortgage or trust deed that secures a construction loan attaches immediately
before the first preliminary notice filing for the construction project if each claimant that has
a preliminary notice on file on the construction project before the mortgage or trust deed
was recorded receives full payment for all construction work the claimant performed before
the mortgage or trust deed was recorded, regardless of whether the claimant receives full
payment before or after the day on which the mortgage or trust deed is recorded.

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.