Utah Code § 11-13-304

Certificate of public convenience and necessity required -- Exceptions
Open in Lexace · Ask the AI about this section
(1) Before proceeding with the construction of any electrical generating plant or transmission
line, each interlocal entity and each out-of-state public agency shall first obtain from the
public service commission a certificate, after hearing, that public convenience and necessity
requires such construction and in addition that such construction will in no way impair the public
convenience and necessity of electrical consumers of the state of Utah at the present time or in
the future.
(2) The requirement to obtain a certificate of public convenience and necessity applies to each
project initiated after the section's effective date but does not apply to:
(a) a project for which a feasibility study was initiated prior to the effective date;
(b) any facilities providing additional project capacity;
(c) any facilities providing replacement project capacity; or
(d) transmission lines required for the delivery of electricity from a project described in
Subsection (2)(a), or facilities providing additional project capacity, or facilities providing
replacement project capacity within the corridor of a transmission line, with reasonable
deviation, of a project producing as of April 21, 1987.