Utah Code § 10-2-817

Electric utility service in annexed area -- Reimbursement for value of facilities --
Open in Lexace · Ask the AI about this section
Liability -- Arbitration.
(1) As used in this section:
(a) "Commission" means the Public Service Commission established in Section 54-1-1.
(b) "Current replacement cost" means the cost the transferring party would incur to construct the
facility at the time of transfer using the transferring party's:
(i) standard estimating rates and standard construction methodologies for the facility; and
(ii) standard estimating process.
(c) "Depreciation" means an amount calculated:
(i) based on:
(A) the life and depreciation mortality curve most recently set for the type of facility in the
depreciation rates set by the commission or other governing regulatory authority for the
electrical corporation; or
(B) a straight-line depreciation rate that represents the expended life if agreed to by the
transferring and receiving parties; and
(ii) to include the gross salvage value of the type of facility based on the latest depreciation
life approved by the commission or other governing regulatory authority for the electrical
corporation, with a floor at the gross salvage value of the asset and in no case less than
zero.
(d) "Electrical corporation" means:
(i) an entity as defined in Section 54-2-1; or
(ii) an improvement district system described in Subsection 17B-2a-403(1)(a)(iv).
(e) "Facility" means electric equipment or infrastructure used to serve an electric customer,
above ground or underground, including:
(i) a power line, transformer, switch gear, pole, wire, guy anchor, conductor, cable, or other
related equipment; or
(ii) a right-of-way, easement, or any other real property interest or legal right or interest used to
operate and maintain the electric equipment or infrastructure.
(f) "Facility transfer" means the transfer of a facility from a transferring party to a receiving party
in accordance with Subsection (3).

(g) "Lost or stranded facility" means a facility that is currently used by a transferring party that will
no longer be used, whether in whole or in part, as a result of a facility transfer.
(h) "Receiving party" means a municipality or electrical corporation to whom a facility is
transferred.
(i) "Transferring party" means a municipality or electrical corporation that transfers a facility.
(2)
(a) If an electric customer in an area being annexed by a municipality receives electric service
from an electrical corporation that is not an improvement district system described in
Subsection 17B-2a-403(1)(a)(iv), the municipality may not, without the agreement of the
electrical corporation, furnish municipal electric service to any electric customer in the
annexed area until the municipality has reimbursed the electrical corporation for the value
of each facility used to serve any electric customer within the annexed area, including the
value of any facility owned by a wholesale electric cooperative affiliated with the electrical
corporation, dedicated to provide service to the annexed area.
(b) If an electric customer in an area being annexed by a municipality receives electric service
from an electrical corporation that is an improvement district system described in Subsection
17B-2a-403(1)(a)(iv), the municipality may not, without the agreement of the electrical
corporation, furnish municipal electric service to the electric customer until the municipality
has reimbursed the electric corporation for the value of the facility used to serve the electric
customer within the annexed area.
(3) The following procedures apply if a municipality transfers a facility to an electrical corporation
in accordance with Section 10-8-14 or if an electrical corporation transfers a facility to a
municipality in accordance with Subsection (2), Section 54-3-30, or 54-3-31:
(a) the transferring party shall provide a written estimate of the transferring party's cost of
preparing the inventory required in Subsection (3)(c) to the receiving party no later than 60
days after the date of notice from the receiving party;
(b)
(i) the receiving party shall pay the estimated cost of preparing the inventory to the transferring
party no later than 60 days after the day that the receiving party receives the written
estimate; or
(ii) if the actual cost of preparing the inventory differs from the estimated cost, the transferring
party shall include the difference between the actual cost and the estimated cost in the
reimbursement described in Subsection (5);
(c) except as provided in Subsection (3)(f), the transferring party shall prepare, in accordance
with Subsection (4), and deliver the inventory to the receiving party no later than 180 days
after the day that the transferring party receives the payment specified in Subsection (3)(b);
(d)
(i) at any time, the parties may by agreement correct or update the inventory; or
(ii) if the parties are unable to reach an agreement on an updated inventory, they shall:
(A) proceed with the facility transfer and reimbursement based on the inventory as submitted
in accordance with Subsection (3)(c); and
(B) resolve their dispute as provided in Subsection (6);
(e) except as provided in Subsection (3)(f), the parties shall complete each facility transfer and
reimbursement contemplated by this Subsection (3) no later than 180 days after the date
that the transferring party delivers the inventory to the receiving party in accordance with
Subsection (3)(c); and
(f) the periods specified in Subsections (3)(c) and (e) may be extended for up to an additional 90
days by agreement of the parties.

(4)
(a) The inventory prepared by a transferring party in accordance with Subsection (3)(c) shall
include an identification of each facility to be transferred and the amount of reimbursement as
provided in Subsection (5).
(b) The transferring party may not include in the inventory a facility that the transferring party
removed from service for at least 36 consecutive months prior to the date of the inventory,
unless the facility was taken out of service as a result of an action by the receiving party.
(5)
(a) Unless otherwise agreed by the parties, the reimbursement for the transfer of each facility
shall include:
(i) the cost of preparing the inventory as provided in Subsection (3)(b);
(ii) subject to Subsection (5)(b)(i), the value of each transferred facility calculated by the current
replacement cost of the facility less depreciation based on facility age;
(iii) the cost incurred by the transferring party for:
(A) the physical separation of each facility from its system, including the cost of any facility
constructed or installed that is necessary for the transferring party to continue to provide
reliable electric service to its remaining customers;
(B) administrative, engineering, and record keeping expenses incurred by the transferring
party for the transfer of each facility to the receiving party, including any difference
between the actual cost of preparing the inventory and the estimated cost of preparing the
inventory; and
(C) reimbursement for any tax consequences to the transferring party resulting from each
facility transfer;
(iv) the value of each lost or stranded facility of the transferring party based on the valuation
formula described in Subsection (5)(a)(ii) or as otherwise agreed by the parties;
(v) the diminished value of each transferring party facility that will not be transferred based on
the percentage of the facility that will no longer be used as a result of the facility transfer;
and
(vi) the transferring party's book value of a right-of-way or easement transferred with each
facility.
(b)
(i)
(A) The receiving party may review the estimation of the current replacement costs of each
facility, including the wage rates, material costs, overhead assumptions, and other pricing
used to establish the estimation of the current replacement costs of the facility.
(B) Prior to reviewing the estimation, the receiving party shall enter into a nondisclosure
agreement acceptable to the transferring party.
(C) The nondisclosure agreement shall restrict the use of the information provided by
the transferring party solely for the purpose of reviewing the estimation of the current
replacement cost and preserve the confidentiality of the information to prevent any effect
on a competitive bid received by either party.
(ii)
(A) If the age of a facility may be readily determined by the transferring party, the transferring
party shall use that age to determine the facility's depreciation.
(B) If the age of a facility cannot be readily determined, the transferring party shall estimate
the age of the facility based on the average remaining life approved for the same type of
facility in the most current depreciation rates set by the commission or other governing
regulatory authority for the electrical corporation.

(c)
(i)
(A) A transferring party that transfers a facility in accordance with this section shall, upon
delivery of a document conveying title to the receiving party, transfer the facility without
any express or implied warranties.
(B) A receiving party that receives a facility in accordance with this section shall, upon receipt
of a document conveying title, accept the facility in its existing condition and assume any
and all liability, fault, risk, or potential loss arising from or related to the facility.
(ii) Notwithstanding Subsection (5)(c)(i), if, within six months after the date that any oil filled
equipment is transferred, the receiving party discovers that a transferred oil filled equipment
contains polychlorinated biphenyl, the transferring party shall reimburse the receiving party
for the cost of testing and disposal of that oil filled equipment.
(6)
(a) If the parties cannot agree on each facility to be transferred or the respective reimbursement
amount, the parties shall:
(i) proceed with the facility transfer and the reimbursement based on the inventory as submitted
by the transferring party in accordance with Subsection (3)(c) and in accordance with the
schedule provided in Subsection (3)(e); and
(ii) submit the dispute for mediation or arbitration.
(b) The parties shall share equally in the costs of mediation or arbitration.
(c) If the parties are unable to resolve the dispute through mediation or arbitration, either party
may bring an action in the state court of jurisdiction.
(d) The arbitrator, or state court if the parties cannot agree on arbitration, shall determine each
facility to be transferred and the amount to be reimbursed in accordance with Subsection (5).
(e) If the arbitrator or state court determines that:
(i) a transferring party transferred a facility that should not have been transferred, the receiving
party shall return the facility;
(ii) a party did not transfer a facility that should have been transferred, the party that should
have transferred the facility shall transfer the facility to the party to whom the facility should
have been transferred;
(iii) the amount reimbursed by the receiving party is insufficient, the receiving party shall pay the
difference to the transferring party; or
(iv) the amount reimbursed by the receiving party is more than the amount that should have
been reimbursed, the transferring party shall pay the difference to the receiving party.
(7) Unless otherwise agreed upon in writing by the parties:
(a) a party shall transfer a facility to be transferred in accordance with Subsection (6)(e) no later
than 60 days after the day that the arbitrator or court issues a determination unless the parties
mutually agree to a longer time to complete the transfer; and
(b) a party shall:
(i) pay an amount required to be paid in accordance with Subsection (6)(e) no later than 30
days after the day that the arbitrator or court issues a determination; and
(ii) include interest in the payment at the overall rate of return on the rate base most recently
authorized by the commission or other governing regulatory agency for the electrical
corporation from the date the reimbursement was originally paid until the difference is paid.
(8)
(a) Nothing in this section limits the availability of other damages under law arising by virtue of an
agreement between the municipality and the electrical corporation.

(b) Notwithstanding Subsection (8)(a), a party described in this section is not entitled to an award
for:
(i) damages that are indirect, incidental, punitive, exemplary, or consequential;
(ii) lost profits; or
(iii) other business interruption damages.
(9) Nothing in this section or Section 10-8-14, 54-3-30, or 54-3-31 applies to a transfer of facilities
from an electrical corporation to a municipality in accordance with a decision by a municipality
that did not previously provide electric service and seeks to commence providing electric
service to a customer currently served by an electrical corporation within the municipal
boundary.
(10) The provisions of this section apply to any annexation under this part.
Renumbered and Amended by Chapter 399, 2025 General Session

‹ Prev All Utah sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.