South Dakota Code § 57A-9-323

Future advances
Open in Lexace · Ask the AI about this section
(a) Except as otherwise provided in subsection (c), for purposes of determining the priority of a perfected security interest under §
57A-9-322
(a)(1), perfection of the security interest dates from the time an advance is made to the extent that the security interest secures an advance that:
(1) Is made while the security interest is perfected only:
(A) Under §
57A-9-309
when it attaches; or
(B) Temporarily under §
57A-9-312
(e), (f), or (g); and
(2) Is not made pursuant to a commitment entered into before or while the security interest is perfected by a method other than under §
57A-9-309
or
57A-9-312
(e), (f), or (g).
(b) Except as otherwise provided in subsection (c), a security interest is subordinate to the rights of a person that becomes a lien creditor to the extent that the security interest secures an advance made more than forty
-
five days after the person becomes a lien creditor unless the advance is made:
(1) Without knowledge of the lien; or
(2) Pursuant to a commitment entered into without knowledge of the lien.
(c) Subsections (a) and (b) do not apply to a security interest held by a secured party that is a buyer of accounts, chattel paper, payment intangibles, or promissory notes or a consignor.
(d) Except as otherwise provided in subsection (e), a buyer of goods takes free of a security interest to the extent that it secures advances made after the earlier of:
(1) The time the secured party acquires knowledge of the buyer's purchase; or
(2) Forty
-
five days after the purchase.
(e) Subsection (d) does not apply if the advance is made pursuant to a commitment entered into without knowledge of the buyer's purchase and before the expiration of the forty
-
five
-
day period.
(f) Except as otherwise provided in subsection (g), a lessee of goods takes the leasehold interest free of a security interest to the extent that it secures advances made after the earlier of:
(1) The time the secured party acquires knowledge of the lease; or
(2) Forty
-
five days after the lease contract becomes enforceable.
(g) Subsection (f) does not apply if the advance is made pursuant to a commitment entered into without knowledge of the lease and before the expiration of the forty
-
five
-
day period.

‹ Prev All South Dakota sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.