If the proposed site for an energy conversion facility or AC/DC conversion facility is located in a county that does not have a comprehensive plan or has not adopted zoning ordinances, the applicant must provide written notice of intent to apply for a permit for the construction of the facility, by certified mail, to each adjacent property owner, at least three months before filing the application as required in § 49-41B-11 .
‹ Prev All South Dakota sections Next ›
Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.