South Carolina Code § 57-5-1630

Extension of construction contracts to include additional work.
Open in Lexace · Ask the AI about this section
No construction contract may be extended to include work not contemplated in the original award, except within the limitations imposed by the contract. Where in the judgment of the Secretary of the Department of Transportation it is in the public's interest and prices advantageous to the department are obtained, the department may extend contracts to include additional work. In every case, the commission must ratify the contract extension at the next succeeding commission meeting. Advertisement in the case of extensions of contracts under this section shall consist of detailed reports of the transactions made public at open meetings of the commission.
Effect of Amendment
2023 Act No. 2, SECTION 1, rewrote the section, providing that the commission is not required to provide preapproval of construction contract extensions and that it must ratify extensions at the next commission meeting.

‹ Prev All South Carolina sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.