Submission of cost estimate for units not completed.
Open in Lexace · Ask the AI about this section
In the case of construction of an electric generating unit begun, but not completed, prior to the effective date, the affected public utility shall, within 30 days after the effective date, submit an estimate of the cost of constructing that unit which was formulated no later than 30 days from the beginning of construction. For the purposes of 66 Pa.C.S. §§ 515 and 1308(f), such estimates shall be deemed to have been filed in accordance with section 515(a). The commission shall promulgate rules and regulations to implement sections 515 and 1308(f) as added by this act.
1984, DECEMBER 21, P.L.1265, NO.240