Pennsylvania Code § 62-3922

Payment of retainage to subcontractors.
Open in Lexace · Ask the AI about this section
In the absence of sufficient reason, within 20 days of the receipt of payment by the contractor, the contractor shall pay all subcontractors with which it has contracted their earned share of the payment the contractor received.
SUBCHAPTER D
PROMPT PAYMENT SCHEDULES
Sec.
3931. Performance by contractor or subcontractor.
3932. Government agency's progress payment obligations.
3933. Contractors' and subcontractors' payment obligations.
3934. Withholding of payment for good faith claims.
3935. Penalty and attorney fees.
3936. Contracts involving Federal aid.
3937. Certain provisions unenforceable.
3938. Applicability.
3939. Claims by innocent parties.

‹ Prev All Pennsylvania sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.