Pennsylvania Code § 12-4305

Scope of work.
Open in Lexace · Ask the AI about this section
(a) Requirement.-- A program shall require for each proposed clean energy project and water conservation project a scope of work, energy baseline or water usage baseline and the projected energy savings or water usage reductions in order to establish the viability of the qualified project and the projected energy savings or water usage reductions.
(b) Verification of completion.-- After a qualified project is completed, the municipality or county shall obtain verification from the qualifying commercial property owner and from an independent professional inspector or building code official that the qualified project was properly completed.