Oregon Code § ORS 701.180

Alternative mediation or arbitration process; waiver and compliance
Open in Lexace · Ask the AI about this section
Notwithstanding the provisions of ORS 36.600 to 36.740, any other provision of law or any contractual provision, failure of a contractor to initiate mediation or arbitration proceedings within 30 days after notification by the Construction Contractors Board of a complaint under ORS 701.145 is a waiver by the contractor of any contractual right to a mediation or arbitration process in lieu of mediation by the board under ORS 701.145. If the parties do not resolve or settle the dispute pursuant to board mediation under ORS 701.145, unless otherwise provided by law regarding a dispute described under ORS 652.140 or 653.010 to 653.261, the complainant must comply with any contractual provision for mediation or arbitration of the dispute as a condition for obtaining the judgment required under ORS 701.145 (5). [Subsection (1) enacted as 1989 c.430 5; subsection (2) enacted as 1989 c.928 21; 1991 c.67 187; 1991 c.181 12; 2001 c.197 17; 2001 c.414 11; 2003 c.598 52; 2007 c.793 21; 2011 c.630 51,71; 2016 c.99 13]
CONSTRUCTION CONTRACTORS BOARD

‹ Prev All Oregon sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.