Oregon Code § ORS 469.067

Dispatchable standby generation program operated by public utility; annual reporting requirements
Open in Lexace · Ask the AI about this section
(1) A public utility, as defined in ORS 757.005, that operates a dispatchable standby generation program to support grid reliability shall, no later than June 1 of each year, report to the Director of the State Department of Energy the following information related to the operation of generators in the program in the previous calendar year:
(a) The aggregated number and nameplate capacity of the generators;
(b) The total and average hours of operation of the generators;
(c) The aggregated amounts of fuels, by type, used annually;
(d) The availability of renewable fuels in the regional market for standby generators in the program; and
(e) Compliance with ORS 469.320 (2)(g)(C)(ii).
(2) Within 30 days of receiving the information reported under subsection (1) of this section, the director shall cause the information to be posted on a publicly available website.