Oklahoma Code § 82-110.8

Title 82. Waters And Water Rights: Notice of completion of construction - Certification
Open in Lexace · Ask the AI about this section
A.  Certificates of completion of works from the Oklahoma Water
Resources Board shall be required before any water may be impounded
by a new dam or before water may be impounded at an elevation higher
than that previously authorized by the Board at an existing dam
which has been modified.  Said certificate shall contain the date of
approval of plans and specifications for the dam, date construction
was completed on said dam, and any other conditions as may be
required by the Board.
B.  The owner must give notice of completion of construction of
the new dam or of modifications to an existing dam to the Board, and
the Board shall inspect such dam before issuing a certificate of
completion.
C.  The Board may modify, revoke or amend any said certificate
as necessary to assure the safety of the dam.
D.  Fees for the inspections and for the issuance of
certificates required by this section shall be set forth in rules

‹ Prev All Oklahoma sections Next ›