A.  A permittee issued a notice or order by the Department
pursuant to the provisions of this act or any person having an
interest which is or may be adversely affected by such notice or
order or by any modification, vacation or termination of such notice
or order, may apply to the Chief Mine Inspector for review of the
notice or order within thirty (30) days of receipt thereof or within
thirty (30) days of its modification, vacation or termination.  Upon
receipt of such application, the Chief Mine Inspector shall cause
such investigation to be made as it deems appropriate.  Such
investigation shall provide an opportunity for a public hearing, at
the request of the applicant or the person having an interest which
is or may be adversely affected, to enable the applicant or such
person to present information relating to the issuance and
continuance of such notice or order or the modification, vacation or
termination thereof.  The filing of an application for review under
this subsection shall not operate as a stay of any order or notice.
The permittee and other interested persons shall be given
written notice of the time and place of the hearing at least five
(5) days prior thereto.  Any such hearing shall be of record.
B.  Upon receiving the report of such investigation, the Chief
Mine Inspector shall make findings of fact, and shall issue a
written decision, incorporating therein an order vacating,
affirming, modifying or terminating the notice or order, or the
modification, vacation or termination of such notice or order
complained of and incorporate his findings therein.  Where the
application for review concerns an order for cessation of surface
coal mining and reclamation operations issued pursuant to the
provisions of this title, the Chief Mine Inspector shall issue the
written decision within thirty (30) days of the receipt of the

application for review, unless temporary relief has been granted by
the Chief Mine Inspector pursuant to this section or by the court.
C.  Pending completion of the investigation and hearing required
by this section, the applicant may file with the Chief Mine
Inspector a written request that the Chief Mine Inspector grant
temporary relief from any notice or order issued together with a
detailed statement giving reasons for granting such relief.  The
Chief Mine Inspector shall issue an order or decision granting or
denying such relief expeditiously.  Where the applicant requests
relief from an order for cessation of coal mining and reclamation
operations, the order or decision on such a request shall be issued
within five (5) days of its receipt.  The Chief Mine Inspector may
grant such relief, under such conditions as it may prescribe, if:
1.  A hearing has been held in the locality of the permit area
on the request for temporary relief in which all parties were given
an opportunity to be heard;
2.  The applicant shows that there is substantial likelihood
that the findings of the Chief Mine Inspector will be favorable to
him; and
3.  Such relief will not adversely affect the health or safety
of the public or cause significant, imminent environmental harm to
land, air or water resources.
D.  Following the issuance of an order to show cause as to why a
permit should not be suspended or revoked, the Chief Mine Inspector
shall hold a public hearing after giving written notice of the time,
place and date.  Any such hearing shall be of record. Within sixty
(60) days following the public hearing, the Chief Mine Inspector
shall issue and furnish to the permittee and all other parties to
the hearing a written decision, and the reasons therefor, concerning
suspension or revocation of the permit.  If the Chief Mine Inspector
revokes the permit, the permittee shall immediately cease surface
coal mining operations on the permit area and shall complete
reclamation within a period specified by the Chief Mine Inspector,
or the Chief Mine Inspector shall declare as forfeited the
performance bonds for the operation.
E.  Whenever an order is issued under this section, or as a
result of any administrative proceeding under this act, at the
request of any person, a sum equal to the aggregate amount of all
costs and expenses, including attorney fees, as determined by the
Chief Mine Inspector to have been reasonably incurred by such person
for or in connection with his participation in such proceedings,
including any judicial review of agency actions, may be assessed
against any party or the Department as the court, resulting from
judicial review or the Chief Mine Inspector, resulting from
administrative proceedings, deems proper.

‹ Prev All Oklahoma sections Next ›