Effective: October 11, 2021 Latest Legislation: Senate Bill 52 - 134th General Assembly The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant. Last updated July 23, 2021 at 4:56 PM
‹ Prev All Ohio sections Next ›