North Dakota Code § 49-22-09.1

Approval of hydroelectric transmission facilities by legislative assembly
Open in Lexace · Ask the AI about this section
required.
After compliance with the applicable requirements of this chapter, any hydroelectric 
transmission facility that transmits hydroelectric power produced outside the United States, and 
which crosses any portion of this state, must have the approval of the legislative assembly by 
concurrent resolution. A person may not begin construction of a hydroelectric transmission 
facility in this state which transmits hydroelectric power produced outside the United States, or 
exercise the right of eminent domain in connection with such construction, without first having 
complied with this chapter and obtained the approval of the legislative assembly. This section 
does not apply to any electric transmission facility for which a route permit and certificate of 
corridor compatibility has been issued prior to July 1, 1985, or any extension thereof issued after 
July 1, 1985.