North Dakota Code § 49-22-08.1

Application for a permit - Notice of filing - Amendment - Designation of a
Open in Lexace · Ask the AI about this section
route.
1. An application for a route permit for an electric transmission facility within a designated 
corridor must be filed no later than two years after the issuance of the certificate and 
must be in such form as the commission may prescribe, containing the following 
information:
a. A description of the type, size, and design of the proposed facility.
b. A description of the location of the proposed facility.
c. An evaluation of the proposed route with regard to the applicable considerations 
set out in section 49-22-09 and the criteria established pursuant to section

‹ Prev All North Dakota sections Next ›