North Dakota Code § 49-22-07.2

Waiver of procedures and time schedules
Open in Lexace · Ask the AI about this section
Any utility which proposes to construct an electric energy conversion facility or an electric 
transmission facility within the state may make an application to the commission for a waiver of 
any of the procedures or time schedules set forth in this chapter or in the rules adopted 
pursuant to this chapter. The commission, upon a finding that the proposed facility is of such 
length, design, location, or purpose that it will produce minimal adverse effects, or, upon a 
finding that a demonstrable emergency exists, may issue an order waiving specified procedures 
and time schedules required by this chapter or by the rules adopted pursuant to this chapter, 
including, but not limited to, applications, notices, and hearings, and may forthwith issue a 
certificate of site compatibility, a certificate of corridor compatibility, or a route permit, with such 
conditions as the commission may require.